Total Access 1248 Octal T1 IMA DSLAM Installation and Maintenance Practice
3-2 61179641L4-5B
Shipping Contents
The shipping container for the Total Access 1248 includes the contents shown in Table 3-1.
Required Tools
The following tools and materials are required to install the Total Access 1248:
•Wire-wrap tool
• #2 phillips-head screwdriver
• #1 phillips-head screwdriver
• Straight-slot screwdriver
• Multimeter (ohmmeter and voltmeter)
• Crimping tool for power lugs
• Wire strippers
• Side cutters
Table 3-1. Total Access 1248 Shipping Contents
Description Part Number Quantity
Total Access 1248 Octal T1 IMA DSLAM 1179641L4 1
Total Access 1248 Octal T1 IMA DSLAM Installation and
Maintenance Practice
61179641L4-5 1
Cable Assembly, Ground Wire 3125P037@ 1
Terminal Block 32024CON10 1
Mounting Bracket, 19-inch 3265540 2
Mounting Bracket, 23-inch 3265541 2
Screw, 8-32 × 1/4 3276003007 4
Screw, 8-32 × 3/16 327611034 4
Cable Tie 3292032 5