QUICKDRAW→ Steam Heater
3.Connect condensate trap inlet parallel to or below the outlet of the heat exchanger. The ability to lift condensate via steam pressure cannot be assured on QuickDraw products due to the possible use of a modulating steam valve (storage units only) or multiple solenoid steam control system. The recommended methods of condensate distribution are:
a.Plumb to a condensate receiver and pump or vacuum return to the condensate return header.
b.Plumb to a pneumatic/electric actuated condensate pump trap for return to the condensate return header.
c.Drain to atmosphere – (would require constant
Inadequate drainage of condensate can adversely affect heat transfer and limit the performance of the water heater. Please note damage to the water heater attributed to poor condensate drainage is not covered in the product warranty.
STEAM VALVES
Two position
CAUTION: Most valve problems are caused by dirt or trash in the steam line. This is most likely to occur during installation. Teflon pipe tape, pipe joint compounds, metal particles and dirt will clog up strainers and orifices and prevent valve seats from closing. Clean all pipe line strainers at
1.When placing the unit into operation, open relief valve to purge air from top of tank and begin to fill the tank with cold water. Check for plumbing leaks. Be sure to fill the tank completely before closing the relief valve.
CAUTION: Do not energize the heater or circulating pump until the tank is full of water. Serious damage may result.
2.Push control switch, located on the control box, to activate the steam valve and thermostats. Check steam valve for operation; the valve solenoid should “click” to open valves when operating switch is pushed “on”. The
Temperature Setting: The operating thermostat is set at the factory at approximately 120°F and the upper operating thermostat is set at approximately 130°F. Make adjustments by turning the thermostat dial to the desired temperature.
3.Push the operating switch, located on the control box, to “off” before opening manual main steam supply valve. This will allow condensate that has collected in the supply line to drain through the trap installed in front of the steam valve. When the steam supply line is free of condensate, push operating switch to “on”, opening the electric
4.Do not operate unit under conditions in excess of those specified on nameplate.
7