2.4 FLOOR STAND INSTALLATION

To install the E or F111/112 onto the floor stand, follow the steps outlined below:

A.Uncrate the floor stand and place in an upright posi- tion.

NOTE

Detailed instructions are included with each floor stand.

B.Place a spirit level across the top of the stand to check for level condition, side to side and front to back. If adjustment is necessary, level the stand by turning the bottom part of each leg in or out, then tighten the lock nut.

WARNING

DO NOT INSTALL CASTERS ON THIS FLOOR STAND. THE STAND IS UNSTABLE WITH CASTERS AND COULD TIP CAUSING SERIOUS IN- JURY.

C.Place supports under freezer, then remove the 4 legs and replace with the rubber stud/plate mounts pro- vided. Mounts must be fully tightened to the freezer.

D.Place the freezer base gasket on the floor stand with the connected seam to the back and angle side up. Center the gasket side to side and 1-3/4 inches from the rear of the floor stand.

E.Place the freezer on the floor stand with the front of the freezer to the door end. All 4 stud/plate mounts must engage the holes in the floor stand. Secure the mounts with the nuts and washers provided. (Fig. 8).

2.5 INSTALLING PERMANENT WIRING

If permanent wiring is required by local codes, the following procedure must be performed.

WARNING

DISCONNECT FREEZER FROM THE SOURCE OF ELECTRICAL SUPPLY BEFORE SERVICING.

A.Remove the back panel.

B.Disconnect the wires from the terminal

block. Disconnect the green ground wire from the grounding stud. (Fig. 9).

Figure 9. Power Cord Connection

C.Remove the power cord.

D.Install permanent wiring according to local code.

E.Replace the back panel.

Figure 8 - Floor Stand

5