Installation of the WLANE-C
Step 1: Unpack the box, check for all components.
Step 2: Make sure the Enclosure is on a level surface. Extend
T Bars |
|
Figure 1 | Level Surface |
|
3/4"
Step 3: Remove one 2x2 or 2x4 ceiling tile from your ceiling grid.
Step 4: Make a 6" x 8" cut in the center of the selected tile. See figure 2.
Installation of the WLANE-C
Step 5: Place enclosure through the hole and make sure the T- bars are resting on the Ts. See figure 3.
|
| 8" | T Braces |
| 21" | 6" | 21" |
2' | T Bars | 8" |
|
|
| 8" |
|
| CeilingTile | 4' |
|
|
|
|
Figure 3
Step 6: The Enclosure should be about 1/4" below the tile. See figure 4.
CeilingTile |
|
|
| 8" |
|
21" | 6" | 21" |
2' | 8" |
|
| 8" |
|
| 4' |
|
Figure 2
6
1/4" |
2' |
CeilingTile |
4' |
Figure 4