NETGEAR GSM7248R manual Installation, Site Requirements for Switch Location

Page 19

Managed Layer 2 Switches GSM7224R and GSM7248R Hardware Installation Guide

Installation

Install the equipment in the following sequence, as presented in this chapter:

1.Select a location. See the following section, “Selecting a Location.”

2.Install the switch. See “Installing the Switch” on page 2-4.

3.Check the installation. See “Checking the Installation” on page 2-5.

4.Apply power and check the LEDs. See “Connecting to Power and Check the LEDs” on page 2-5.

Selecting a Location

The switch can be mounted in a standard 19-inch (48.26-centimeter) rack, wall mounted, or left freestanding (placed on a tabletop). The site where you install the switch can greatly affect its performance. Before installing the switch or switches, make sure that the chosen installation location meets the following site requirements.

Table 2-1. Site Requirements for Switch Location

Requirements

Mounting

Desktop Installations. Provide a flat table or shelf surface.

 

Rack-mount Installations. Use a 19-inch (48.3-centimeter) EIA standard

 

equipment rack that is grounded and physically secure, and the rack-mounting kit

 

supplied with your switch.

 

 

Access

Put the switch in a position that lets you access the front panel RJ-45 ports, view the

front panel LEDs, and access the rear panel power connector.

 

 

 

 

Provide a power source within 6 feet (1.8 meters) of the installation location. Power

Power source

specifications for the switch are shown in Appendix A, “Default Settings and

Technical Specifications.” Be sure that the AC outlet is not controlled by a wall switch,

 

 

which can accidentally turn off power to the outlet and the switch.

 

 

Environment

Install the switch in a site free from strong electromagnetic field generators (such as

 

motors), vibration, dust, and direct exposure to sunlight.

 

 

Temperature

The ambient switch operating temperature range is 0º to 55ºC (32º and 131ºF). Keep

 

the switch away from heat sources such as direct sunlight, warm-air exhausts, hot-air

 

vents, and heaters.

 

 

Operating humidity

Install the switch in a dry area with a maximum relative humidity of 90%,

 

noncondensing.

 

 

Hardware Installation

2-3

v1.0, November 2007

Image 19
Contents NETGEAR, Inc Voluntary Control Council for Interference Vcci Statement Certificate of the Manufacturer/ImporterEN 55 022 Declaration of Conformance Product and Publication Details Contents Chapter Troubleshooting Conventions, Formats, and Scope About This ManualHow to Print This Manual How to Use This ManualIii Page GSM7224R Front Panel and LEDs Chapter IntroductionGSM7248R Front Panel and LEDs GSM7224R Rear PanelDescription GSM7248R Rear PanelInterpreting the LEDs LED DescriptionsSPD/Link/ACT LED Safety InstructionsV1.0, November V1.0, November Package Contents Chapter Hardware InstallationUnpacking the Hardware Protecting Against Electrostatic DischargeSite Requirements for Switch Location InstallationRequirements Installing the Switch Checking the Installation SFP Modules Connecting a Redundant Power Supply RPSConnecting a Console to the Switch Connecting Equipment to the SwitchConsole port Problem Cause Solution Chapter TroubleshootingTroubleshooting Chart Troubleshooting ChartNetwork adapter cards Additional Troubleshooting SuggestionsDhcp Appendix a Default Settings and Technical SpecificationsDefault Settings Table A-1. Default Configuration SettingsGvrp ACLGmrp Table A-2. Technical Specifications Technical SpecificationsFeature GSM7224R GSM7248R Mtbf ARPStorage OperatingV1.0, November Document Link Appendix B Related DocumentsV1.0, November