2.2.2Removing an I/O Module Blank From the Chassis

1.Unlock the I/O Module Blank by pushing the red latch release button.

2.Pull the locking arm down to a position perpendicular to the front of the chassis.

3.Pull the I/O Module Blank out of the chassis using the locking arm.

2.2.3Installing the Mellanox M4001[F, Q] Switch Into the Dell Chassis

Make sure the rack is stable on a solid floor and that the rack is filled from the bottom up. This will keep the center of gravity as low as possible reducing risk of tipping.

Refer to the Dell PowerEdge M1000e Hardware Owners Manual for more information.

1.Follow the instructions in Section 2.2.1 or Section 2.2.2 to remove an old switch or an I/O Module Blank.

2.On the new switch, push the red latch release button.

3.Pull the lever forward until the lever is perpendicular to the front panel.

4.Push the switch into the slot until the latching mechanism is against the bar.

5.Push the lever on the latching mechanism up, making sure that the latching mechanism catches the locking bar. The lever should now be parallel to the front panel.

6.Check the indicator lights to make sure the switch has power.

The rack mounting is designed to fit the PowerEdge Chassis. Take precautions to guar- antee proper ventilation for air intake at the front of the chassis and exhaust at the rear in order to maintain good airflow at ambient temperature. Cable routing in particular should not impede the air exhaust from the chassis.

2.3Power Connections and Initial Power On

The I/O module will automatically power up when AC power is applied. There is no power switch. Immediately upon closing the latching mechanism check to make sure that the green switch LED is lit.

2.4InfiniBand Cable Installation

All cables can be inserted or removed with the unit powered on. To insert a cable, press the con- nector into the port receptacle until the connector is firmly seated. The green LED indicator accompanying each port will light when the physical connection is established (that is, when the unit is powered on and a cable is plugged into the port with the other end of the connector plugged into a functioning port). After plugging in a cable, lock the connector using the latching mecha- nism particular to the cable vendor. The yellow LED will light if the subnet manager is running (non blinking indicating that no data is being transferred yet). When a logical connection is made the yellow LED will blink signifying data is being transferred.

14

Mellanox Technologies

Image 14
Contents PN M4001F, M4001Q Rev Document Number Contents Revision History Revision History TableRelated Documentation About this ManualIntended Audience Online ResourcesRev Overview InfiniBand Connectors Switch Front Panel and Locking MechanismSwitch Status Lights IOM states and LED configurationsI2C Interface RJ-45 Connector I2C RJ-45 InterfaceInstallation and Basic Operation Installation Safety WarningsRack Mounting and Servicing Copper InfiniBand Cable Connecting/DisconnectingEquipment Installation Equipment DisposalMechanical Installation Rear View of the Dell PowerEdge M1000e ChassisPower Connections and Initial Power On InfiniBand Cable InstallationMellanox Technologies Updating Firmware Cluster Management and FirmwareNetwork Management and Clustering Software Troubleshooting Appendix a Specifications M4001F, Q Specification DataPhysical Power and Environmental Scalability and Performance Appendix B EMC Certification Statements EN55022 Class a Statement Class a StatementMIC Certification Korea InfiniBand Qsfp Connector Pinout Appendix C Qsfp InterfaceGND Appendix D Avertissements de sécurité d’installation Codes électriques locaux et nationaux Appendix E Installation Sicherheitshinweise Regionale und nationale elektrische Bestimmungen