Nortel Networks 50 Series manual Quick Install Guide

Page 1

BES50_QuickInstallGuide4.pdf 9/13/2006 3:12:23 PM

BusinessBES50Ethernet Switch 50 Series

Quick Install Guide

Mounting Options

 

Steps 4 10

 

You can download all documents

The BES50FE12/24T and BES50GE12/24T switch units can be

 

referenced in this Quick Install guide at

mounted horizontally on a flat surface and stacked with a BCM50.

 

www.nortel.com.

 

4

 

4. If you mount a BES50 unit on a desktop or shelf,

 

Steps 1

3

 

 

 

1

 

attach the supplied rubber feet to the bottom of the

 

Before you

 

unit. If the BES50 system includes additional units,

 

 

 

you can set the additional units beside, or stack

 

start

 

 

 

 

 

them on top of, the first unit.

 

1. Download the Business Element

 

 

 

 

5

 

 

 

 

Manager 1.0 Installer to a

 

5. If you are mounting the additional units

 

 

 

computer on your network. You

beside the first unit, attach the supplied

 

 

 

install the Element Manager in

 

 

 

rubber feet to the bottom of each unit.

 

2

 

Step 16.

 

 

 

 

 

 

6

 

6. If you are stacking the additional units on top of

 

 

 

 

the first unit, mount each unit into the tabs on top

 

2. Confirm that you have the tools and

 

of another unit.

 

package contents as follows:

7

 

 

 

Tools Required:

 

 

 

 

a. Phillips or flathead screwdriver, depending

 

 

C

on the type of screws used.

 

 

 

 

 

M

Package contents:

 

7. If you mount the switch on a

 

 

Y

b. BES50FE-12/24T PWR or

desktop or flat surface, attach the

 

BES50GE-12/24T PWR switch

four adhesive feet to the device as

CM

c. Adhesive foot pads (4)

indicated.

 

 

 

 

 

MY

d. AC power adapter

 

 

 

CY

BES50-FE/GE-12T PWR switch

a. Set the device on a flat surface near an AC power source, making

 

sure there are at least two inches of space on all sides for proper air flow.

 

System Indicators

Port/PoE Status Indicators

CMY

b. If you install multiple switches, attach four adhesive feet to each one.

 

 

 

 

 

 

 

K

 

 

 

Place each device squarely on top of the one below, in any order.

 

 

 

 

 

 

 

 

8

8. To install a BCM50 unit on top of a BES50 unit, place

 

 

RJ-45 Ports with PoE

the BCM50 unit on top of the BES50.

 

 

 

 

Steps 11 13

Powering up

 

!

Perform steps 11 and

 

12 in the order listed.

11

11. Insert the power adapter

into the DC power socket in the

front of the switch.

12

12. Plug the other end of the power adapter into a grounded, 3-pin socket, AC power source.

13

13. Check the front-panel LEDs as the device powers on to confirm that the PWR LED is green. If not, check that the power cable is correctly plugged in.

The BES50 series switch performs a short self-test as soon as you connect the switch to the power supply. The status LED will flash green during the self-test, then solid green when finished. If the Status LED turns off, the device is not working correctly. When the self-test finishes, the BES50 starts switching data.

17

17. Enter the range 192.168.1.1 to 192.168.1.255 and then click OK.

Note: By default the Read Community is “PlsChgMe!RO” and the Write Community is “PlsChgMe!RW”.

18

18. Select the BES device from the list of

tree.network elements on the Element Manager

19

19. Click the Web Page button on the

Element Manager menu.

 

20

20. Enter the default username

 

(nnadmin) and password

 

(PlsChgMe!) to log on to the

21

BES50.

 

 

 

 

 

21. From the main menu, choose Administration > Quick Start. The Quick Start screen appears showing the IP address and other items that you can optionally configure. If you want to manually assign IP addresses, refer to Using the Nortel Business Ethernet Switch 50 at www.nortel.com.

BES50-FE/GE-24T PWR switch

9

9. Make sure the feet of the BES50 are in the slots

System Indicators

Port/PoE Status Indicators

 

 

on the top of the BCM50 unit and in front of the slots

 

 

 

 

 

10

10. Slide the unit back until it clicks in place on

14

Steps 14 21

Initial Access and Configuration

RJ-45 Ports with PoE

RJ-45 Ports

the slots.

 

 

3

3. Check your cables; when you install

 

 

the switch into a network make sure you

 

 

use the following required cables:

 

 

• Category 3 UTP or STP cables with an RJ-45 connector

 

 

(for 10BASE-T ports).

Slots

Feet

 

 

• Category 5 UTP or STP cables with an RJ-45 connector

 

 

(for 100BASE-TX ports).

 

 

• Category 5, 5e, or 6 UTP or STP cables with an RJ-45

 

 

connector (for 1000BASE-T ports).

 

 

N0128198

14. To access the BES50, first install the Business Element Manager 1.0. Refer to Element Manager documentation at www.nortel.com for instructions.

 

 

15

15. Start the Element Manager.

You are now ready to use the BES50 series switch in

 

 

 

 

 

 

your network installation.

16

16. From the Element Manager

Refer to Using the Nortel Business Ethernet Switch 50

menu, choose Network > Find

at www.nortel.com for detailed installation

Network Elements > Business

instructions.When you connect a PC directly to the

 

 

Ethernet Switch.

BES50, use the default IP address 192.168.1.128

 

 

 

 

 

 

 

 

 

 

Image 1
Contents Quick Install Guide