Siemens TPS3 09 Sheet for specs & wire-outs, May be required, To not drop SPD into wall

Page 5

VCAUTION

CONDUCTING DIELECTRIC AND/OR HI-POTENTIAL TESTING WILL CAUSE INTERNAL DAMAGE TO TPS3 UNIT.

Do not perform dielectric or high potential

tests with the TPS3 unit installed.

V DANGER

Hazardous voltage.

Will cause death or serious injury.

Keep Out.

Qualified personnel only.

Disconnect and lock off all power before working on this equipment.

TPS3 09 Installation Instructions

Pre-Plan your installation. You need to accomplish the following:

• Meet all National and Local codes (NEC® Article 285 and UL

1449 address SPDs)

• Confirm System voltage to SPD voltage (120V SPD will fail

instantly on 240V, 277V, etc.)

• Mount SPD as close to panel or equipment as possible to keep

leads short (long leads hurt performance substantially)

• Ensure leads are as short and straight as possible, including

neutral and ground. If using a breaker, use a breaker position

that is close to the SPD and the panel’s neutral & ground

• If using a breaker, recommended breaker size is 30A due to

10 AWG conductor

• Make sure system is grounded per NEC® and clear of faults

before energizing SPD (inadvertent system problem may fail

SPD).

• Never Hi-Pot test Any SPD (will prematurely fail SPD)

A B C

BREAKER

N

G

Use closest breaker to SPD

Locate SPD close to intended breaker

Keep Leads Short as Possible

Avoid Sharp Bends

• Do not install the TPS3 09 through the bottom of a NEMA

3R panel. Dripping water will prematurely fail the SPD.

1. Use voltmeter to check voltages and ensure correct SPD. See Data

Figure 4: Typical Flush Mount Installation

Mounting Surface

Mounting Screws

 

Sheet for specs & wire-outs

2.

Determine Mounting location – weather resistant equipment

 

may be required

3.

If SPD has optional Dry Contact and Flush Mount Kit, pre-plan

 

their installation. See Figures 4&6. (If flush mounting, be careful

(4 places, through mountingplate into mounting surface, screws not provided)

Removed Material

Flush Mount Plate

SPD

 

to not drop SPD into wall)

4.

Remove power from panel/source. Confirm panel/source is

 

deenergized.

5.

Identify breaker location and SPD location. Position SPD such that

 

LEDs are best visible.

6.

Mount SPD – weather resistant applications require additional

 

sealing, o-rings, etc. (not included)

 

--

Remove an appropriately sized knockout from panel.

 

--

Connect conductors as appropriate – short and straight as possible

 

--

(Hi-Legs are Phase B)

 

Note that the metallic connection hub is not grounded within the SPD

 

 

and proper grounding requires connection of the green conductor

 

 

ground.

7.

Label or mark conductors as appropriate (neutral: white, ground:

 

green, energized: black, hi-leg: orange)

8.

Make sure system is bonded per NEC® and is clear of hazards or

 

faults before energizing (N-G bonding not per NEC® will fail SPDs:

 

#1 cause of SPD failures)

9.

Energize and confirm proper operation of green LED indicators

 

and/or options.

Flush Mount Kit Screws

(8-32 x 5/8” Thread Cutting, 4 places, through plate into SPD)

Phase, Ground,

and Neutral Wires

Figure 5: Lead Lengths

Leads: Short & Straight

Cut Excess; Do Not Coil or Loop

X

CUT OFF EXCESS

 

LENGTH

DO NOT LOOP OR

Not

 

COIL

Good

 

 

Goodp

SHORT &

 

STRAIGHT

 

 

Image 5
Contents TPS3 Do Not Hi-Pot Test SPDs Bonding and Grounding HazardIntroduction NEC Art 285 & ULVoltage Rating & Application Specifications240/120V 1Ø, 3W Plus Ground 208Y/120V 3Ø, 4W Plus GroundRemove power from panel/source. Confirm panel/source is Sheet for specs & wire-outsDetermine Mounting location weather resistant equipment May be requiredBlue Normally Closed Gray Common Red Normally Opened Limited Warranty Maintenance12.09.09 #8173