Step 3 Select power supply method

When you use the 5V power adapter, connect the pins 2 and 3 of the 3-pin connector(marked as ‘POWER-SWITCH’) using a jumper cap, as shown in the following figure.

When you use the USB 5V power supply, connect the pins 1 and 2 of the 3-pin connector(marked as ‘POWER-SWITCH’) using a jumper cap, as shown in the following figure.

Step 4 Connect the USB cable with the host.

If you select using USB 5V power supply on Step 3, the LED indicator of power as shown in the following figure lights up.

Issue 01 (2013-02-08)

Huawei Proprietary and Confidential

8

Copyright © Huawei Technologies Co., Ltd.

 

 

Image 8
Contents Development Kit Guide No Warranty Scope About This DocumentRevision History Contents Introduction to the DVK OverviewAbout This Chapter 1shows the placement of the DVK Installation and Use Guide Installation and Power-On ProcedureIssue 01 Huawei Proprietary and Confidential Issue 01 Huawei Proprietary and Confidential Interface Functions Power Switch and Power Supply ModeInterface Functions of the DVK LED Indicators USB Communication InterfaceUsim Card Interface Antenna ConnectorButtons Acronyms and Abbreviations Acronym or Abbreviation Expansion
Related manuals
Manual 58 pages 62.46 Kb