Spalding M8660411 manual Side View, Build drainage hill

Page 6

4.

 

Fill hole with concrete. Tamp down concrete to release air pockets

 

and build drainage hill.

DRAINAGE HILL

1" (2.54 cm)

PLAYING SURFACE

 

SIDE VIEW

5.

Insert J-bolts (19) from mounting plate (2) into cement as shown. Move assembly around to release

 

any air pockets in cement, then rest mounting plate on cement drainage hill. Apply some pressure to

level mounting plate on top of drainage hill. Level mounting plate and square with playing surface. Clean off any excess cement on mounting plate at this time and place washers (24) on J-bolts (19).

IMPORTANT!

Check leveling of mounting plate several times with carpenter’s level while concrete is curing.

IMPORTANT!

 

Front of mounting plate

 

(2) must be parallel with

PLAYING SURFACE

playing surface.

 

24

24

24

2

24

IMPORTANT!: WAIT A MINIMUM OF 72 HOURS BEFORE GOING ON

TO NEXT STEP. CONCRETE MUST CURE. ALLOW ADDITIONAL TIME

FOR COLD, WET OR HUMID WEATHER.

ID# M8660411

09/05

6

Image 6
Contents High End Residential In-Ground Basketball System Safety Instructions Parts List Hardware Identifier Bolts & Screws Make sure nuts 25 are 2.75 7 cm from top of J-bolts Side View Build drainage hillInsert bushings 38 into areas ShownPlaying Surface Mounting plate 2 as shownCompleted Assembly ID# M8660411 09/05 Attach elevator adjustment 12 to Lower yokeAttach elevator adjustment 12 to pole bracket Yokes 18 Using TWO people to hold the boardAttach backboard 10 to upper and lower First attach board 10 to upper yokeEnd of the rod 14 as shown Figure a Install net 4 to rim as shown Apply height indicator labels 32 & 31 to height indicatorsAttach height indicators To lower yoke in areaNing 09/05 ID# M8660411 Check system leveling. Pole Should be level in all directionsLimited Lifetime Warranty