CHARGING THE ACCUMULATOR
ACCUMULATOR TESTING PROCEDURE
To check or charge the accumulator the following equip- ment is required:
•Accumulator Tester (Part Number 02835).
•Charging Kit Assembly (P/N 31254); (includes a regulator, hose and fittings).
•NITROGEN bottle with an 800 psi/56 bar minimum charge.
1.Remove the charging valve plug from the post driv- er.
2.Holding the chuck end of Stanley tester (P/N 02835), turn the gauge fully
3.Thread the tester onto the charging valve of the tool accumulator (do not advance the
4.Advance the valve stem by turning the
5.If pressure is OK unscrew the
6.Install the charging valve cap (or plug).
ACCUMULATOR CHARGING PROCEDURE
1.Perform Steps 1 through 4 of the Accumulator Test- ing Procedure above.
2.Connect the chuck of the charging assembly to the charging valve on the accumulator tester or, if preferred, remove the tester from the tool charging valve and connect the charging assembly chuck di- rectly to the tool charging valve.
3.Adjust the regulator to the charging pressure of 600 psi/42 bar.
NOTE:
It may be necessary to set the regulator at 650– 700
4.Open the valve on the charging assembly hose.
5.When the accumulator is fully charged close the valve on the charging assembly hose and remove the charging assembly chuck from the accumulator tester of tool charging valve.
6.If the accumulator tester has been used, be sure to turn the
7.Replace the
Guage
Chuck
Tester
Charging
Valve
Accumulator Tester (P/N 02835)
Location Of Charging Valve
Figure 2. Charging the Accumulator
PD45 User Manual ◄ 11