SECTION 10: OPERATION AND MAINTENANCE

SECTION 10: OPERATION AND MAINTENANCE

WARNING

Explosion Hazard

Installation, service and annual inspection must be done by a contractor qualified in the installation and service of gas-fired heating equipment or your gas supplier.

Turn off gas and electrical supplies before performing service or maintenance.

Failure to follow these instructions can result in death, injury or property damage.

Read this manual carefully before installation, operation, or service of this equipment. All components are accessed via the door secured by four sheet metal screws. Opening the door exposes live electrical connections and hot components.

10.1 Pre-Start-Up Checks

All pre-start-up checks must be carried out before lighting the heater.

Ensure that the heater and all controls are suitable for the gas, pressure and electrical supply to which they are to be connected.

10.1.1 Electrical Checks

1.Check that all site wiring is connected in accordance with the appropriate wiring diagram on Page 18, Section 9.3.

10.1.2 Gas Supply

All aspects of the gas installation including the gas meter must be inspected, tested for gas tightness and purged in accordance with local and national codes.

Ensure that the air is fully purged from the heater inlet pipe up to the main gas valve inlet test nipple.

10.1.3 Mechanical Checks

1.Check that the flue (and air intake for separated combustion units) is installed in accordance with these instructions and local regulations.

10.2 Begin Start-Up

10.2.1 Before Operating the Heater

To ensure that all the controls are in safe working order, operate the heater for the first time with the isolating gas valve turned off and power supply turned on.

1.Turn off the isolating gas valve.

2.Turn up the thermostat above room

temperature. The automatic ignition sequence will now begin as described on Page 22, Figure 11.

There will be no ignition of the burner and lockout will occur, which proves the controls are operating correctly.

21

Image 27
Contents Combat Page Roberts-Gordon LLC Page Table of Figures Page Manpower Requirements Heater SafetyWall Tag Installer ResponsibilityCorrosive Chemicals National Standards and Applicable CodesClearances to Combustibles Minimum Required Installation ClearancesCritical Considerations 3.1 Basic Information Manufactured UnitsVent VentilationGas Supply Electrical SupplyNational Standards and Applicable Codes High Altitude Duct Heater Installation 5.1 General Temperature Rise and Pressure Drop RangesMinimum Inlet Duct Length Suspension Air Flow And Temperature Rise RangesUnited States Requirements Vent InstallationVenting Changing Vent and Air Intake OrientationHorizontal Venting Standard Vented Heaters Models Uhdxr 150Separated Combustion Heaters Models Uhdxsr 150 Unvented OperationMaximum Vent Lengths Vent MaterialReplacing an Existing Heater in a Venting System Standard Vented Heater Common Vertical Vent Termination Concentric Vent Box UHVK1 Building Ventilation Separated Combustion InstallationUnvented Installation AIR SupplyConnections GAS PipingWiring Positioning ThermostatsLow Voltage Thermostat with One Heater L2 L1 Internal Wiring DiagramFlue Blower Transformer GAS Valve Flame Sensor Electrode Ladder Wiring DiagramElectrical Connection to the Heater Mechanical Checks Operation and MaintenancePre-Start-Up Checks Electrical ChecksEND View TOP View External Controls Pressure SwitchCheck Gas Rate Turning Off the HeaterUser Instructions Servicing Objects Maintenance ChecklistVicinity of the Heater Vehicles and OtherBurner Observation When installed DuctworkGas Line and Shut-off ValvesGeneral TroubleshootingConduct start-up procedure as shown on Page 21, Section Troubleshooting For Automatic Ignition Burner SystemsTroubleshooting for Flame Supervision System Troubleshooting for Flue Blower Troubleshooting for Gas ValvesBurner Components Replacement PartsBurner Injectors Burner CompartmentIgnition Electrode and Flame Probe Uhdxsr Ignition Control Limit Switches Removal and ReplacementUHD Specifications 15.1 Dimension DataTechnical Data Table General Technical Data TableLimitations on Authority Representatives Warranty is Void ifRoberts Gordon will PAY for Roberts Gordon will not PAY forPage Owner Warranty Registration Card Page Page Clearances to Combustibles