VENTING INSTALLATION INSTRUCTIONS Installation Planning

VENTING INSTALLATION INSTRUCTIONS

Continued

INSTALLATION PLANNING

There are two basic types of direct-vent installation:

Horizontal Termination

Vertical Termination

Horizontal Termination Installation

IMPORTANT: Horizontal square terminations require only in- ner portion of wall firestop. Horizontal installations using round termination require exterior portion of wall firestop (see Figure 14, page 10).

1.Set the fireplace in its desired location and determine the route your horizontal venting will take. Do not secure the fireplace until all venting has been installed. Some installations require sliding the fireplace in and out of position to make final vent- ing connections. Figures 14 through 18 on pages 10 through 12 show different configurations for venting with horizontal termination that will help you decide which application best suits your installation. Check to see if wall studs or roof rafters are in the path of your desired venting route. If they are, you may want to adjust the location of the fireplace.

2.Direct vent pipe sections and components are designed with special twist-lock connections.

Twist-Lock Procedure: The female ends of the pipes have locking lugs (indentations). These lugs will slide straight into matching slots on the male ends of adjacent pipes. Push pipe sections together and twist one section clockwise approxi- mately one-quarter turn until the sections are fully locked (see Figure 8). Note: Horizontal runs of vent must be supported every three feet. Use wall straps for this purpose.

3.Use a 45° elbow to connect venting system to fireplace flue collar. The elbow is designed to be twist-locked onto the flue collar as described in step 2. IMPORTANT: Do not attempt to alter the configuration of the elbow by cutting, twisting, bending, etc.

4.Assemble the desired combination of pipe and elbows to the fireplace flue collar. If there are long portions of venting run, pre-assembled pipe sections may be installed as subassemblies for convenience.

5.Carefully determine the location where the vent pipe assembly will penetrate the outside wall. The center of the hole should line up with the center-line of the horizontal vent pipe. Mark the wall for a 10 3/4" x 10 3/4" square hole. Cut and frame the square hole in the exterior wall where the vent will be terminated. If the wall being penetrated is constructed of noncombustible material, such as masonry block or concrete, a 8 1/2" hole with zero clearance is acceptable (see Figure 9).

Male

Female Slots

Locking

Lugs

Figure 8 - Vent Pipe Connections

Vent Opening

 

Combustible Wall

10 3/4" Inside Framing

10 3/4"

(273 mm)

(273 mm)

 

10 3/4"

 

(273 mm)

 

(Framing

Vent Opening

Detail)

 

Noncombustible Wall

 

8 1/2"

 

(216 mm)

 

 

Center

 

of Hole

Figure 9 - Vent Opening Requirements

www.desatech.com

116240-01B

Image 8
Contents For Your Safety For Your Safety What to do if YOU Smell GASTable of Contents Safety InformationProduct Identification Local CodesLocation and Space Requirements Product FeaturesPRE-INSTALLATION Preparation Clearances Framing and Finishing13 1 41 5/8 16 3/4 48 48 1/4 81 1/2 58 1/2Location of Termination CAP Termination CAP AIR Supply Inlet GAS MeterVenting Installation Instructions Installation PrecautionsInstallation Planning Horizontal Termination InstallationMale Female Slots Locking Lugs CenterVent Cap Wood Screw Interior Wall Surface Firestop Vent CapHorizontal Vent PipeHorizontal Termination Configurations Snorkel Termination Minimum Vertical30 max Venting with Two 90 Elbows Installation for Vertical Termination Flat Ceiling InstallationRoof Flashing Wall Strap Elbow Ceiling Firestop If area above is a room orVertical Termination Configurations Elbow Into inner collar fireplace as shownHigh Altitude Installation Venting Installation Fireplace Installation Check GAS TypeInstalling Optional Blower Accessory Desa 5/8 Pipe & Vent KitsFireplace Installation Model BKT InstallationInstallation Items Needed Installing GAS Piping to Fireplace LocationBlower Wiring Diagram Checking GAS Connections Connecting Fireplace to GAS SupplyPressure Testing Gas Supply Piping System Removing Louver Panels Pressure Testing Fireplace Gas ConnectionsREMOVING/REPLACING Glass Door Removing Glass Door Installing Lava Rock and Glowing EmbersCleaning Glass Door Installing Brick Liner Models BL42DASA and BL42DHASA Wall Switch InstallationOptional Remote Control Installation Model WRC Extension Cord IgnitionWiring Diagram Operating FireplaceLighting Instructions Equipment PilotOperating Optional Blower Accessory To Turn OFF GAS To ApplianceOptional Remote OperationCleaning Maintenance Glass DoorPilot and Burners LogsTroubleshooting Observed Problem Possible Cause RemedyGas leak. See Warning statement at Replacement Parts Service HintsTechnical Service Parts Under WarrantySpecifications Illustrated Parts Breakdown Models KC42NE, KC42PE, VKC42NE and VKC42PEParts List Illustrated Parts Breakdown KEY Part Number Description Accessories Date Purchased Serial Number BrandModel Industrial Drive Box Bowling Green, KY 116240-01B Industrial Drive P.O. Box Warranty InformationModel Serial No Date Purchased