5.Place two beads of black silicone sealant (1” in from the edge) on the front and both sides of the
6.Remove wood blocks and lower the ice machine onto the
7.Seal the front edge of the base insulation to the bin with white silicone sealant.
Install Mylar Strip between Evaporator and Bulkhead
Mylar will cover the joint where the bulkhead attaches to the base. It will extend from the left sidewall past the water inlet fitting.
1.Remove screws (right and left side) that secure the evaporator to the bulkhead.
2.Remove three screws located between the evaporator and water inlet line. Remove the screw holding the water inlet fitting.
3.Determine bin switch wire location and cut a slot in the top edge of the mylar strip (adhesive edge = top).
4.Apply silicone sealant at the bin switch wire entrance and the left side corner (4” each direction) where the base and bulkhead meet.
5.Pull evaporator away from bulkhead. Place bottom of mylar strip in sump trough and slip up behind evaporator (align slot cut in step 3 with bin switch wire). Mylar must extend above bottom evaporator mounting screw (approximately 2” above gasket/bulkhead joint).
6.Remove paper backing from mylar. Apply tension to mylar and work toward the ends to eliminate wrinkles, as the tape is pressed to the bulkhead.
7.Align evaporator extrusion and bulkhead screw holes; puncture mylar for the bottom screw holes and insert screws. Install all remaining evaporator screws.
8.Puncture mylar and insert screws removed in step 2.
Bulkhead and Sidewall Insulation
1.Using the supplied insulation as a template, cut and remove the fiberglass insulation (approximately 9” from base to top of cut). Using a putty knife, scrape insulation and glue from the bottom of the bulkhead on the rear and both sides.
2.Remove upper white backing to expose tape surface (do not remove backing below slit at bottom). Slide the insulation down into the base and then press the insulation against the bulkhead to secure. Insulation must bottom out on the base and be tight to the fiberglass insulation.
Insulation must extend all the way into the base.
3.Repeat step 2 on the left side bulkhead.
8005493 Sheet 2 of 3 06/02/00
4.The back panel insulation will rest in a bed of silicone. Apply a continuous bead of black silicone sealant to the base of the ice machine next to the bulkhead wall.