![](/images/new-backgrounds/1040680/4068035x1.webp)
Pull and connect the
*The sealant between
TOP VIEW
90° MAXIMUM BEND
FIGURE 23
Apply
FIGURE 24
Check the level or slope of the venting again, and adjust if required.
SLOPE
FIGURE 25
OFFSET VENT ARRANGEMENT
CONDITION 1:
Where a straight vent arrangement is impossible, a horizontal 90 degree maximum bend can be made. Use the water heater casing outer diameter as a template to form the corrugated tube.
FIGURE 26
CONDITION 2:
Where floor joists impede venting, a rise to complete the vent termination is possible. All installations require 1 in. (25mm) clearance to combustibles.
Note:
A. The maximum horizontal vent length of 80 in. (2.03m) minus wall thickness should be considered when installing an offset vent arrangement.
B. Do not combine condition 1 (Figure 26) with condition 2 (Figures 27 & 28) in the same installation.
C. The maximum allowable drop from vent
>1 in. (25mm) | >1 in. (25mm) |
|
WALL 10 in. (254mm) (REF)
MINIMUM
68 in. (1.72m) FOR
40 gal. MODELS AND
76 in. (1.93m)
FOR 50 gal. AND
50 gal.
FIGURE 27
>1 in. (25mm) | >1 in. (25mm) |
|
7.25 in. (184mm)
MAX
WALL 10 in. (254mm) (REF)
MINIMUM
68 in. (1.72m) FOR
40 gal. MODELS AND
76 in. (1.93m)
FOR 50 gal. AND
50 gal.
FIGURE 28
18