Site Preparation – Installation Space Requirements
16 AIS® 3000 10-40kVA, 400V, Site Preparation and Installation Manual – 990-2258
Clearance for stand-alone 352mm Enclosures
*) All physical installations must comply with all national standards.
Space requirements mm
Minimum clearance above UPS (A) 0
UPS depth (B) 854
UPS width 352
Minimum free rear space for ventilation* (D) 100
Minimum front clearance (E) 1000
No side clearance required (add width of Stabilizing Bracket for floor anchoring if
applicable)*
0
Stabilizing Bracket width 85
Total installation depth, inclusive of Front Panel, and minimum front and rear
clearances (F)
1954