Briggs & Stratton 71013 System Setup, You must perform the following before operating the system

Models: 71013

1 44
Download 44 pages 2.59 Kb
Page 8
Image 8

8.Cut two pin connector ends off of current transformer leads and discard. Strip wires and place in supplied wire connectors.

9.Using installer supplied 300VAC or greater wire, run wires from wire connectors to control module terminal block labeled “CT1A” through “CT2B” in power management system.

10.Using installer supplied 300VAC or greater wire, connect C (Common) and NO (Normally Open) terminals on terminal strip J9 of control module in transfer switch to control module terminal block labeled “TXSF” and “TXFG” in power management system.

Location of J9 Terminal Strip in Transfer Switch

11.Wire the air conditioner thermostat control wiring to the control module labeled “AC1A-AC2B” in power management system.

NOTE: AC1A and AC1B is for the priority 1 air conditioner. AC2A and AC2B is for the priority 2 air conditioner.

12.For 120VAC selected loads, remove wire from selected load circuit breaker.

13.Using installer supplied 300VAC or greater wire, connect selected load circuit breaker to terminal block at power management system labeled “CB/B1” for priority 1 load.

14.Using installer supplied 300VAC or greater wire and a wire nut, connect the selected load wire to terminal block in power management system labeled “RLY/B1” for priority 1 load.

15.Repeat steps 12 through 14 for all other 120VAC priorities using terminals “CB/C1” through “RLY/D2”.

16.For 240VAC selected loads, remove both wires from selected load circuit breaker and place in load side of installer supplied contactor.

17.Using installer supplied 300VAC or greater wire, connect circuit breaker to line side of contactor.

18.Using installer supplied 300VAC or greater wire, connect one pole of the circuit breaker to terminal block in power management system labeled “CB/B1” for a priority 1 load.

19.Using installer supplied 300VAC or greater wire, connect Neutral in main breaker panel to contactor coil.

20.Using installer supplied 300VAC or greater wire, connect contactor coil to terminal block in power management system labeled “RLY/B1” for a priority 1 load.

21.Repeat steps 16 through 20 for all other 240VAC priorities using terminals “CB/C1” through “RLY/D2”.

22.Tighten all wire connections/fasteners to proper torque. See inside power management system enclosure for proper torque values.

System Setup

You must perform the following before operating the system:

Place the switch labeled “SW2” on the control module in the NG or LP position, whichever is appropriate for the installed home standby system.

 

SW2

 

 

SW3

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Place the switch labeled “SW3” on the control module to match the rating of the home standby system.

In main breaker panel, turn selected load circuit breakers to the ON position.

IMPORTANT: After installation of the power management system is complete, turn on utility power to the home standby generator and transfer switch. Wait one minute before turning generator to AUTO.

6

BRIGGSandSTRATTON.COM

Page 8
Image 8
Briggs & Stratton 71013 manual System Setup, You must perform the following before operating the system