2 Assembly

Villa Assembly

Column Placement

Reference your column placement chart for the particular villa you purchased. The center point measurements will be described for your particular sized villa. Please locate these dimensions and mark them on your floor or professionally laid slab. If your municipality requires a footing please see our recommendations for proper column installation.

Anchoring the Main Support

Post

When scoring the concrete, make sure that the mark is dark enough to see, as you will be drilling a hole in the concrete. This hole will be where the anchoring bolt is located. Also, it is the owner’s responsibility to obtain a 1/2” masonry bit. This bit will be used to drill the anchoring holes in the foundation. A masonry bit may be bought at any local hardware store.

Refer to Figure 1 for steps 1 through 3.

1.Pre-drill the anchoring hole using a 1/2”masonry drill bit (see NOTE above). Drill the hole to a depth of no less than 3”. Using a hammer, insert the anchoring bolt by gently tapping the bolt into place. Continue to tap into place until the anchoring bolt is seated securely in the hole.

2.After drilling the hole and inserting the anchoring bolt, slide the main support post assembly on to the anchoring bolt and tighten down using the provided hardware.

3.Repeat these steps for all four corners of the villa.

Figure 1. Anchoring the main support post

www.calspas.com

2009 Villa

LTR20091034, Rev. A

Page 4
Image 4
Cal Flame Spa Home Resort manual Villa Assembly, Column Placement, Anchoring the Main Support Post