6
It is of outmost importance that the clearanc es to combustible materials be scrupulously
respected upon installation of the stove you have selected. Refer to the tables below :
Single pipe / Double pipe
A
B
C
D
E
F
29”
30”
39”
34-3/4”
22”
32”
Floor to ceiling height must be at least 7' (84") in all cases.
The clearance between the f lue pipe and a wall are valid only f or vertical walls and for
vertical flue pipe.
The flue pipe must no t go through roof trussing, an attic, a wardrobe, a floor, a
combustible partition, or similar spaces.
A flue pipe crossing a combustible wall must have a minimum clearance of 18".
To reduce flue pipe clearances from combustible materials, contact your local safety
department.
For reduced clearances refer to NFPA 211 table 9-6.6.1.