Standby Generator Sets
Service Schedule
Maintenance | Level 1 |
| Level 2 |
| Level 3 |
| Level 4 |
| Level5 |
|
Tasks | Recom- | Task | Required | Task | Required | Task |
| Task | Required | Task |
| mended | Comp. | to be done | Comp. | to be done | Comp. | Required | Comp. | to be done | Comp. |
| to be done | (Date- | 3 months/ | (Date- | Semi- | (Date- | to be done | (Date- | Bi- | (Date- |
| monthly/ | Initials) | Initials) | annually/ | Initials) | Annually/ | Initials) | annually/ | Initials) | |
| 10 hrs. |
| 30 hrs. |
| 50 hrs. |
| 100 hrs. |
| 250 hrs. |
|
1.Disable the unit from operating
per the first page warning.
2.Check the engine
oil level. Adjust as necessary.
3.Check the engine coolant level. Adjust as necessary.
4.Check the engine coolant thermal
protection level. Correct as necessary.
5.Check the natural gas delivery system for leaks
and correct pressure on gas engine driven units. Tighten connections as necessary.
6.Check the air inlets and outlets for debris. Clean as necessary.
7.Check the battery electrolyte level and specific gravity if accessible. Adjust as necessary.
8.Check the battery
posts, cables, and charger for loose connections, corrosion, and proper operation. Correct as necessary.
9.Check the unit wiring for loose connections, corrosion, and damage. Correct as necessary.
09/05 A .Rev SrvSchd001