Specifications

WEATHER AND MAINTENANCE KITS

To keep the generator running at its peak, the following kits are offered:

Cold Weather Kit

~Recommended for climates with temperatures below 32° F.

Extreme Cold Weather Kit

~Recommended Block Heater Kit for protection in tempera- tures below 32° F.

Scheduled Maintenance Kit

~Kit includes the recommended parts to maintain the genera- tor. Refer to the Service Schedule for regular maintenance intervals.

For additional information, or to order any of these kits, please contact an Authorized Service Dealer or Customer Service Representative.

RECONFIGURING THE FUEL SYSTEM

NOTE:

All models are configured to run on natural gas from the fac- tory.

Before the generator can be operated using a LP fuel source, the fuel system and control panel (refer to the installation drawing for location) must be reconfigured. The steps to reconfigure the generator from a natural gas (NG) to a liquidified petroleum (LP) fuel source are as follows:

FUEL SYSTEM

1.Turn the main gas supply off and disconnect the battery.

2.Remove the carburetor fuel hose from the outlet port of the demand regulator (see Figure 6.1).

3.Disconnect the power wires from the fuel solenoid located on top of the regulator assembly by removing the screw on the front of the connector and pulling the connector forward, away from the solenoid body.

4.Loosen the spring clamp on the small fuel enrichment line and remove the hose from the hose barb.

5.Remove the black pipe assembly from the outlet port of the demand regulator. The solenoid assembly may need to be removed before performing this operation (Figure 6.1).

6.Remove the NG fuel jet (loosen counter clockwise) from the outlet port.

7.Remove the LP fuel jet (loosen counter clockwise) from the jet keeper port on the side of the regulator housing. Install this jet into the outlet port in the regulator casting.

NOTE:

The jet sizes are stamped on the individual jets. The larger jet size is used for running on NG.

8.Install the previously removed NG jet into the jet keeper port on the side of the regulator housing.

9.Install the previously removed black pipe onto the outlet port of the demand regulator. Use pipe sealant on the pipe threads.

10.Reverse steps 1-4 in this procedure to reactivate the demand regulator.

11.Follow the instructions in the Control Panel section.

Serious injury, including death, or damage will occur if not configured properly. Please consult an Authorized Dealer with any ques- tions.

Figure 6.1 — Reconfigure the Fuel System

CONTROL PANEL

The FUEL TYPE must be reconfigured in the control panel to finalize the conversion process. This generator is configured at the factory to operate on natural gas. If conversion to LP is required, please complete the mechanical conversion process and then call 888-9ACTIVATE for the control panel password. This fuel selection conversion is required to be password protected by Environmental Protection Agency [EPA] regulations.

Whenever the Generator’s Fuel Regulator is converted from one Fuel type to the other, the Control Panel must be reconfigured for the correct fuel type. Failure to convert both the Regulator and Control Panel will result in decreased performance and an increase in emissions, and is a violation of EPA regula- tions.

GenSpec082.RevC12/11