Section 3 — Operation

Generac GTS “W” Type Transfer Switch

Failure to do so may result in damage to cer-

!tain rotary equipment.

8.Set the generator’s main circuit breaker (CB1) to its OFF or OPEN position.

9.Set the Auto/Off/Manual switch to the OFF posi- tion to shut down the generator.

NOTE:

Do NOT proceed until generator AC output voltage and frequency are correct and within stated limits. If the no-load voltage is correct but no-load fre- quency is incorrect, the engine governed speed probably requires adjustment. If no-load frequen- cy is correct but voltage is not, the voltage regula- tor may require adjustment.

3.4GENERATOR TESTS UNDER LOAD

1.Set the generator's main circuit breaker to its OFF or OPEN position.

2.Manually actuate the transfer switch main con- tacts to their emergency (Standby) position. Refer to Manual Operation on page 5.

3.To start the generator, set the AUTO-OFF- MANUAL switch to MANUAL. When engine starts, let it stabilize for a few minutes.

4.Turn the generator's main circuit breaker to the ON or CLOSED position. The generator now pow- ers all LOAD circuits. Check generator operation under load as follows:

Turn ON electrical loads to the full rated wattage/amperage capacity of the generator.

DO NOT OVERLOAD.

With maximum rated load applied, check voltage and frequency across transfer switch terminals E1 and E2. Voltage should be greater than 230 volts; frequency should be greater than 59 Hz.

Let the generator run under rated load for at least 30 minutes. With unit running, listen for unusual noises, vibration, overheating, etc., that might indicate a problem.

5.When checkout under load is complete, set main circuit breaker of the generator to the OFF or OPEN position.

6.Let the generator run at no-load for several minutes. Then, shut down by setting the AUTO- OFF-MANUAL switch to its OFF position.

7.Move the switch's main contacts back to the UTILITY position. For example, load connected to utility power supply. Refer to Manual Operation on page 5. Handle and operating lever of transfer switch should be in down position.

8.Turn on the utility power supply to transfer switch, using whatever means provided (such as a utility main line circuit breaker). The utility power source now powers the loads.

9.Set the generator's AUTO-OFF-MANUAL switch to its AUTO position. The system is now set for fully automatic operation.