3 – Installation of the cables for EPO, external communication and set in parallel :
In order to ensure a good positioning of the different strands of cables on the front panel, it is necessary to follow the recommendations of installation below :
Do separate the strands of fine wire from the power cables along their progress.
Parallel configurations :
A torus ferrite provided with the parallel devices, in order to guarantee the EMC class A level, must be installed like indicated on the figure below ;
External |
| |
cubicle cables |
| |
not supplied | EPO cable | |
(max. 1.5 mm²) | ||
To be clamp | ||
| ||
| separately | |
| Not supplied | |
| (max. 2.5 mm²) |
MGE UPS SYSTEMS | 3 |
Addenda du manuel d’installation 5103056000_AB