4
Fix Bracket “C” to the power unit
with the nuts and washers supplied
(Items “A” on the schematic on page
5). Please ensure that the bracket is
installed as shown to enable full ac-
cess to the square plastic black box
and the metal electrical junction box.
Slide Bracket “B” over Bracket “C”
(once again ensure full access to the
plastic and electrical boxes is main-
tained) and fix it in place, at the
previously calculated length using
the machine screws denoted by
items “B” on the schematic on page
5.
Check that the plastic flaps at the
exhaust outlet for the fan move
freely and have not become jammed
during ship ping or whilst working
with the power unit. Connect an
appropriate length of ducting to the
unit.
Figure 2
Attaching the Range Hood to the Ceiling
The entire structure that has been
pre-assembled above, must now be
hoisted up to the ceiling. A few
things have to happen at once here:
the slots (as discussed below) need
to be engage d and the ductwork
must make connection with the
length of ductwork on the structure.
Do not fix the ducting to the outlet
with screws - use DUCT TAPE.
Stand the assembled structure on a
clean soft surface. Ens ure the
underside of the hood does not get
scratched and slide the chimneys of
the assembled structure from the top
down as per the schematic on page
5. Ensure that the holes for fixing
the decorative chimney are correctly
orientated with the holes at the top
of bracket “A”.
This will require two strong people –
do not attempt this step on your
own. Bracket “B” has slots, position
C per Diagram “A” (refer to page 5),
at the top that will receive the spring
clips located on Bracket “A” – THIS
IS A TEMPORARY HOLD ONLY –
DO NOT RELY SOLELY ON
THESE CLIPS TO HOLD THE
HOOD UP – THEY WON’T. Once
“hooked” by the spring clips immedi-
ately secure the structure with the
machine screws at point “E” on the
schematic on page 5 – THIS MUST
BE DONE IMMEDIATELY AND
SHOULD NOT BE SKIPPED.
Ensure the entire structure is sturdy
- serious injury, death and MAJOR
damage could result should the unit
not be well connected to the frame
structure within the ceiling.
This is of utmost importance – do
not go any further until this has been
tested and double checked the
installer has sole responsibility for
the safe installation of this product.
Connecting Electricity and Ducting
Make sure power is turned off at the
sou rce . Mak e th e e lec tri cal
connection (see figure 2). Test the
functioning of the hood. Slide the
upper chimney into place and attach
with the machine screws provided to
Bracket “A”.