INSTALLATION INSTRUCTIONS
COMMISSIONING
1.COMMISSIONING
1.1Close all openable doors and windows in the room. Ignite the stove and operate on maximum for 10 minutes. Remove the plastic sight plug from the
1
1.2If there are any extractor fans in adjacent rooms, the test must be repeated with the fans running on maximum and interconnecting doors open.
IF SPILLAGE PERSISTS, DISCONNECT THE APPLIANCE AND SEEK EXPERT ADVICE.
For future reference record the installation details on the Appliance Commissioning Checklist of these instructions.