a)Full intent of these specifications, and provide complete submittal including literature, wiring diagrams, fuel piping diagrams, and a list of similar installations.
b)Submittal to be presented to specifying engineer at least seven working days for approval before bid opening. Substitutions are not permitted after contract is awarded.
c)Energy Management Control System(s) must be tested and approved for installation with specified boiler by boiler manufacturer.
B.Boiler construction
1.Boiler sections
a)Assembled with tie rods.
b)Parallel ground sealed with high temperature silicone sealant to assure permanent
c)Sealed
d)Provided with sufficient tappings to install required controls.
2.Boiler(s)
a)Provided with
b)Provided with expansion tank tapping to divert separated air to expansion tank.
c)Constructed to provide balanced water flow through entire section assembly using single supply and return connections for water. No external headers are necessary.
d)Designed with a low silhouette to provide maximum headroom.
e)Elastomer sealing rings are to be used to provide permanent
f)Shipped with insulated heavy gauge steel jacket(s) with split top for easy servicing and coated with durable powdered paint enamel finish.
C.Boiler foundation(s):
Installer to construct needed support and level concrete foundation(s) where boiler room floor is uneven or will not support the weight of the boiler(s).
D.Boiler trim:
1.All electrical components to be of high quality and bear the U.L. label.
a)Water boiler(s) controls furnished:
1)High temperature limit setting to be 140 – 240 degrees.
2)Combination
3)ASME certified pressure relief valve, set to relieve at 30 PSIG. Optional relief valves available up to and including maximum allowable pressure. Side outlet discharge type; contractor to pipe outlet to floor drain or near floor, avoiding any area where freezing could occur.
2