Generac 005262-0 START-UP Checklist, ‹ Preparation for START-UP, ‹ START-UP Inspection

Page 14

Standby Generator Sets

Installation

START-UP CHECKLIST

Before working on the generator, ensure the fol- lowing:

The AUTO/OFF/MANUAL switch is in the OFF position.

The 120VAC supply to the battery charger is switched OFF.

‹PREPARATION FOR START-UP

Ensure that the 120VAC circuit breaker to the bat- tery charger is open.

Remove the fuse from the the control panel. For the H-100 and R-series: Open the front door of the control box and remove the 15 Amp ATO fuse in the lower left-hand corner of the control box.

Connect the battery cables to the battery. Attach negative battery cable last.

Close the 120VAC circuit breaker to the battery charger.

Measure the voltage at the battery before and after the charger is turned on.

Verify all AC electrical connections are tight at the circuit breaker and transfer switch.

Visually inspect entire area looking for loose paper, plastic wrappings, leaves, etc.

Check all hoses clamps fittings for leaks or dam- age.

Check all electrical plugs throughout the genera- tor. Ensure each plug is seated correctly and fully inserted into its receptacle.

Verify the AUTO/OFF/MANUAL switch is in OFF position.

Open the valve to the engine fuel line.

Bleed the fuel system of air. (necessary for long fuel lines).

Open the generator main line circuit breaker.

Connect a manometer to the gas line and record the static pressure. It must be as listed in the Specifications.

Insert the fuse into the control panel.

Move the AUTO/OFF/MANUAL switch to the MAN- UAL position. The engine should now crank and start.

Check voltage at the generator terminals.

For 3-phase units, check phase rotation at the transfer switch terminals. The generator phase rotation must match the utility phase rotation.

Check for coolant, fuel, oil, and exhaust leaks.

Close the generators main line circuit breaker.

Turn the generator set off.

Connect the UTILITY supply to the transfer switch.

Set the AUTO/OFF/MANUAL switch to AUTO.

Disconnect utility power before the transfer switch.

Engine should start, transfer to load.

Run at least 15 minutes on generator power. Make certain all 3-phase loads are functioning correctly (correct phase rotation).

Reconnect Utility power

Transfer switch will transfer back to Utility and engine will shut down within the given time parameters set up for the specific transfer switch and controller.

Install all covers, access plates and door panels.

Put the Owners Manual in a safe and accessible place.

Make certain the AUTO/OFF/MANUAL switch is in the AUTO position.

‹START-UP INSPECTION

When a start-up is performed by an Authorized Service Dealer, a standard three-part form titled “Start-up Inspection for Standby Power Systems” (part no. 067377), should be completed by the instal- lation technician or engineer. See page 1-3 for infor- mation on locating the nearest Authorized Service Dealer. The installer should complete the form and disseminate copies as follows:

White copy: Mail to Generac Warranty Department, P.O. Box 340, 211 Murphy Dr., Eagle, WI 53119- 2062.

Pink Copy: For service file of installing dealer.

Yellow Copy: For the customer’s records.

01/06 B .Rev Install001

8-2

Image 14
Contents Model Standby Generator Sets Table of Contents  Warning   Electrical Hazards  Authorized Service Dealer Location ‹ Operation and Maintenance‹ HOW to Obtain Service IntroductionIdentification Record ‹ Data LabelCoolant Recommendations Equipment DescriptionEngine OIL Recommendations Engine Protective Devices ‹ Natural GAS Fuel System Fuel System‹ Fuel Requirements ‹ LP Fuel SystemSpecifications ‹ Reconfiguring the Fuel System ‹ Cold Weather KIT‹ 3-PHASE Alternators Alternator Power Winding Connections‹ FOUR-LEAD, SINGLE-PHASE Stator Generator AC Lead ConnectionsInitial Inspection for QT Genset Startup InstallationPreparation Before START-UP ‹ START-UP Inspection START-UP Checklist‹ Preparation for START-UP ‹ Engine START-UP and Transfer Operating Unit with Manual Transfer SwitchGenerator Control Operation ‹ Retransfer and ShutdownCooling System Checking Fluid LevelsMaintenance Owner Operator can Perform ‹ Spark Plugs ‹ Changing the Engine AIR Cleaner ‹ Coolant Change‹ Changing Engine OIL ‹ Battery Miscellaneous Maintenance‹ Cleaning the Generator ‹ Battery MaintenanceService Schedule KW 150 KW Standby GAS Engine Driven Generator SetsMaintenance Level 11-3 11-4 Troubleshooting Guide Problem Cause CorrectionStandby Generator Sets Standby Generator Sets Standby Generator Sets Page PAN CB Conn BOX Page UL Circuit Breaker QJ-2P Page Instr Hypot Test not Shown Page C2 Units Page Components Included in 0F9696E Page Weldment Frame 2.4L C2 Page Battery Tray C1 CPL Page Engine 2.4L Hyundai Page Weldment Radiator Support 2.4L Page Gasket Bosch 32 Page Flange Fuel Inlet Page Rear Wrap C2 CPL Page Exhaust Elbow 2 1/4 OD 2 1/2OD Page Page Standby Generator Sets Warranty