Brocade Communications Systems 6720 Rack installation for a Brocade VDX, Verifying operation

Page 6

ATTENTION

Do not connect the switch to the network until the IP address is correctly set. For instructions on how to set the IP address, see “Setting the switch IP address.”

Rack installation for a Brocade VDX 6720

Follow the installation instructions shipped with the appropriate rack mount kit:

To install the switch into a fixed-rail rack, refer to the Fixed Rack Mount Kit (24”-32”) Installation Procedure or the Fixed Rack Mount Kit Installation Procedure.

To install the switch into Telco 2-post rack, refer to the Flush Mount Rack Mount Kit Installation Procedure.

Providing power to the switch

Perform the following steps to provide power to the Brocade VDX 6720.

1.Connect the power cords to both power supplies, and then to power sources on separate circuits to protect against AC failure. Ensure that the cords have a minimum service loop of 6 in. available and are routed to avoid stress.

2.Power on the power supplies by flipping both AC switches to the “I” symbol (VDX 6720-24 only, power supplies for VDX 6720-60 power up automatically when plugged in). The power supply LEDs display amber until POST is complete, and then change to green. The switch usually requires several minutes to boot and complete POST.

ATTENTION

Power is supplied to the switch as soon as the first power supply is connected and turned on.

Verifying operation

After you have powered the system on and POST is complete, verify that the switch is working properly.

1.Verify that the power supply LEDs are solid green.

2.Verify that the system status LED is solid green.

3.The port LEDs should be lit during POST activities. When POST is complete, only the LEDs for ports connected to other devices should be green.

Refer to the Brocade VDX 6720 Hardware Reference Manual for more details on the LED patterns.

Creating a serial connection

You perform all configuration tasks in this guide using a serial connection from a workstation or terminal to the switch.

Complete the following steps to create a serial connection to the switch.

6 of 12

Brocade VDX 6720 QuickStart Guide

 

Publication Number: 53-1002085-02

Image 6
Contents Brocade VDX Brocade Communications Systems, Incorporated Items included with the Brocade VDX Installation and safety considerationsOverview Electrical considerationsEnvironmental considerations Cabinet considerationsStandalone installation for a Brocade VDX Items required for installationRecommendations for cable management Verifying operation Rack installation for a Brocade VDXProviding power to the switch Creating a serial connectionAssigning permanent passwords Changing the default account passwordsUsing Dhcp to set the IP address Setting the switch IP addressEnabling and disabling Brocade VCS mode Enabling VCS modeDisabling VCS mode Configuring switch portsConnecting network devices Installing and connecting an SFP+ transceiverBrocade VDX 6720 QuickStart Guide Connecting to Ethernet or fast Ethernet hubs Connecting to workstations, servers, or routersConnecting a network device to a fiber port Brocade VDX 6720 QuickStart Guide