Installation & Safety Guide | 7 |
Procedure
1.If you have any optional expansion modules, install them first.
The
•
•
These instructions ship with individual expansion modules, and are also available from www.alliedtelesis.com/support/software.
Note that if you insert or remove a module when the switch is already powered on, you must restart the switch before you can use the module.
2.Place the switch in its operating location. If installing the switch in a rack:
•Remove the rubber feet on the bottom of the switch with a
•Attach the two
3.Mount the switch in the rack using
4.Install any SFPs.
You can install optional SFP (Small
Warning Do not look into the optical ports of SFP cables or transceivers. Invisible laser radiation may be emitted from disconnected fibres or connectors.
In both SFP ports, the SFP transceivers must be inserted with the release lever hinge at the bottom. Use the following figure as a guide.