Eaton Electrical IT-RSS, XT-40, IM01005012E instruction manual Power Up and System Checkout

Page 10

IM01005012E

XT-40 & IT-RSS Installation

 

 

2.8Power Up and System Checkout

Apply system power and observe that the LED(s) on the front of the SPD should glow. One LED should glow for each Phase voltage being monitored.

Should there be a significant difference in brightness, check the phase rotation of the panel and ensure that the SPD’s Phase wires are connected to the correct phase. Slight differences in brightness DO NOT indicate a faulty device, rather specification tolerance differences of the indicator circuit’s components. LED brightness symmetry and/or level do not indicate the SPD’s operational status.

Page 8

Rev. 1 – 2/2007

Image 10
Contents IM01005012E Innovative Technology Tvss Products XT-40 & IT-RSSRegister Your Warranty On-Line at Scope IT-RSS System Wiring and Maximum VoltagesXT-40 Catalog Numbering System Safety Precautions Installation Before InstallationXT-40 Wiring Diagrams Single Phase 1P101, 1P201 Split Phase 1S101IT-RSS Wiring Diagram Installing Circuit Interrupt DevicesConduit Installation Mounting the SPDWiring SPD to Electrical System XT-40 & IT-RSS Mounting DimensionsPower Up and System Checkout XT-40 & IT-RSS Installation IM01005012E USA