American Power Conversion 60-80kW 208/480V manual Start UPS from complete power down, UPS start-up

Page 7

Stop/Start UPS and Operating the External Service Bypass

The UPS is now isolated. Maintenance/repair, disconnection or removal can now be carried out.

CAUTION!

Recharge batteries out of service every 3 months to prevent damage.

WARNING!

Internal DC capacitor may contain energy even after the UPS has been switched off. Allow for automatic discharge by waiting at least 5 minutes after switching off UPS and battery breakers before working on the UPS.

2.4Start UPS (from complete power down)

2.4.1 UPS start-up

CAUTION!

Make sure all cable connections are in place prior to first start-up.

NOTICE!

After first system start-up, check that battery temperature is displayable (press and simultaneously on the display – it reads NV (not valid) if incorrectly installed). A battery capacity test is recommended after the electric installation.

NOTICE!

If for any reason the start-up procedure is interrupted, wait for the display to show the step 4 message: “Stop charge DC capacitors : YES” and repeat procedure from there.

CAUTION!

Do not close the MCCBs in the Battery Breaker Box unless the display reads: “Insert fuse or close MCCB” – otherwise the UPS may be damaged. If the display reads “DC capacitor charge error”, do not close MCCB.

Call for assistance.

WARNING!

If “Autostart” is active the UPS will start automatically after step 9 (with a 1-minute delay)

 

990-4035

 

 

User Guide APC Silcon 60-80kW 208V/480V UPS

7

Image 7
Contents Copyright 2000 APC Denmark ApS APC Silcon 60-80kW 208/480V UPS User GuideUser Guide APC Silcon 60-80kW 208V/480V UPS Safety Symbols used in this manualThank You Contents Introduction IntroductionDisplay Unit Stop UPS for stand-by Stop/Start UPS and Operating the External Service BypassStart UPS from stand-by Switching off the UPS Stop UPS for complete power downUPS start-up Start UPS from complete power downSystem start-up now completed Bypassing the Single System UPS Operating the External Service Bypass Switch single systemsUPS YES Bypassing the Parallel UPS System All UPSs Acoustic alarm sounds for 30 secs Stop/Start UPS and Operating the External Service Bypass Set input switches Q001 to position Isolating one UPS in a Parallel/Redundant System Stop/Start UPS and Operating the External Service Bypass Operation OperationKeyboard Batt. load Batt. tank Display of Measured ValuesEconomy Mode Using the Remote DisplayParameter Settings Parameter SettingsParameter Settings Programming Keys Switching to Bypass OperationProgramming Example Load power xx% Mode Comments Alarms and EventsAlarms and Events Displaying the Alarm StackAlarms Description Action Possible AlarmsUnlock Rectifying Alarm Messages Correction of false alarm situations during service Parallel Operation AlarmsBattery Capacity Test Maintenance & TestingMaintenance & Testing Battery Monitoring TestUntil Warranty WarrantyAPC Silcon UPS Limited Factory Warranty APC Denmark How to Contact APCHow to Contact APC APC CorporateUser Guide APC Silcon 60-80kW 208V/480V UPS User Guide APC Silcon 60-80kW 208V/480V UPS