4 DT RS Machines – Care and Use
4.5Compatibility
Note that there is no difference in line up procedure between the T ascam
4.6Maintenance
Check the head hours regularly (see below). Every 250 hours the unit should be cleaned manually and the tape path alignment checked. T his should be performed by an experienced engineer with the correct tools and test tapes. Every 1000 hours the machine should be fully aligned with probable replacement of the pinch roller and reel tables and the possible replacement of the heads. Real world experience has shown that the heads last for between 750 and 1200 hours.
4.7Cleaning
T he error rate of a known good tape should be checked regularly (see below – if the error LED lights it’s far too late!). When the error rate begins to rise, a cleaning tape should be used and then the errors checked again. I f there is no improvement, the machine should be cleaned manually and
4.8Head hour display
T o invoke the head hour display, hold ST OP+PLAY whilst powering on. T he display will say “d XXXX” where XXXX is the total head hours
4.9Error rate display
Hold FF+ST OP+PLAY and power on. Within 2 seconds press ST OP (for DA88) or PLAY (for
4.10T ape gets stuck inside
I f errors occur, sometimes the machine won’t eject, for “safety” reasons. T o eject, enter test mode as above. I nstead of pressing REMOT E, press EJECT . T he tape will now eject. Next turn off the machine and back on to exit test mode. I f the tape is damaged, do not continue to use the machine!