STEP 5 (See Diagram 5 & Cable Loop Diagram)
A.) | Attach the 142” Upper Cable (#35) to the opening at the front of the Upper |
| Frame (#4). Note: The Ball Stopper on the cable should be underneath the |
| Frame. |
B.) | Attach a Pulley (#63) to the opening. Secure it with one M10 x 2 3/8” Allen Bolt |
| (#71), two Pulley Bushings (#50), and one M10 Aircraft Nut (#85). |
C.) | Draw the Cable towards the back of the machine to the opening on the Upper |
| Frame. Repeat the Procedure B above to install another Pulley. |
D.) | Draw the Cable around the Pulley then pull back towards the opening on the |
| Front Press Base (#11). |
E.) | Attach a Pulley to the opening on the Front Press Base. Secure the Pulley with |
| one M10 x 5 1/8” Allen Bolt (#68) and M10 Aircraft Nut (#85). |
F.) | Draw the Cable around the Pulley then to the opening on the Upper Vertical |
| Frame (#14). Repeat Procedure B above to install another Pulley. |
G.) | Draw the Cable around the Pulley then downward. Attach the Cable to a Double |
| Floating Pulley Bracket (#31). Install another Pulley. Let the bracket hanging for |
| now. |
H.) | Pull the Cable upward to the open bracket underneath the Upper Frame. Install a |
| Pulley to the bracket. |
I.) | Pull the Cable downward between the two Guide Rods to the Selector Rod |
| (#17). Fully thread the bolt at the end of the Cable into the top opening on the |
| Selector Rod. |
J.) | Connect the Lat Bar (#18) to a Short Chain (#49) with a |
| connect the Short Chain to the Upper Cable with another |
14