STEP 7 (See Diagram 7 & Cable Loop Diagram)
A.) Attach the 128” Lower Cable (#36) to the open bracket on the bottom of the Leg Developer (#7).
B.) Attach a Pulley to the bracket. Secure it with one M10 x 1 ¾” Allen Bolt (#72), two Ø ¾” Washers (#83), and one M10 Aircraft Nut (#85).
C.) Draw the Cable underneath the Pulley to the opening on the Leg Developer Holder (#1). Attach a Pulley to the opening. Secure it with one M10 x 2 3/8” Allen Bolt (#71), two Pulley Bushings (#50), and one M10 Aircraft Nut (#85).
D.) Draw the Cable underneath the Pulley along the Main Base Frame to the opening on the bottom of the Lower Vertical Frame (#3). Repeat Procedure C above to install another Pulley.
E.) Pull the Cable upward to the Crossed Double Floating Pulley Bracket (#20) previously installed in
F.) Draw the Cable around the Pulley then downward to the open bracket on the Main Base Frame. Install another Pulley.
G.) Pull the Cable around the Pulley then upward to the Double Floating Pulley Bracket (#31) previously installed in
H.) Draw the Cable around the Pulley then pull downward to the bracket on the back of the Upper Vertical Frame (#14). Secure the Cable to the bracket with one M10 x 1” Allen Bolt (#73), two Ø ¾” Washers (#83), and one M10 Aircraft Nut (#85).
I.) Adjust the tension of the Cable by adjusting the Pulley position on the Double Floating Pulley Bracket (#31). If the cables are too loose, move up the Pulley. If the cables are too tight, move down the Pulley.
J.) For best performance of the machine, adjust the Cables so the Selector Stem (Top Plate) on the weight stack is ¼” above the first plate. While pinning the weight stack, push down on the Selector Stem to close up the gap then pin the plates. This will remove the slag in the cable system so the range of motion is smooth and tight.
K.) Connect the Shiver Bar (#19) to a Long Chain (#48) with a
17