Carrier 25HPA6 Check Equipment and Job Site, Install on a Solid, Level Mounting Pad, Unpack Unit

Page 2

25HPA6

INSTALLATION RECOMMENDATIONS

NOTE: In some cases noise in the living area has been traced to gas pulsations from improper installation of equipment.

1.Locate unit away from windows, patios, decks, etc. where unit operation sound may disturb customer.

2.Ensure that vapor and liquid tube diameters are appropriate for unit capacity.

3.Run refrigerant tubes as directly as possible by avoiding un- necessary turns and bends.

4.Leave some slack between structure and unit to absorb vi- bration.

5.When passing refrigerant tubes through the wall, seal open- ing with RTV or other pliable silicon-based caulk. (See Fig. 1.)

6.Avoid direct tubing contact with water pipes, duct work, floor joists, wall studs, floors, and walls.

7.Do not suspend refrigerant tubing from joists and studs with a rigid wire or strap which comes in direct contact with tubing.(See Fig. 1.)

8.Ensure that tubing insulation is pliable and completely sur- rounds vapor tube.

9.When necessary, use hanger straps which are 1 in. wide and conform to shape of tubing insulation. (See Fig. 1.)

10.Isolate hanger straps from insulation by using metal sleeves bent to conform to shape of insulation.

When outdoor unit is connected to factory-approved indoor unit, outdoor unit contains system refrigerant charge for operation with AHRI rated indoor unit when connected by 15 ft. (4.57 m) of field-supplied or factory accessory tubing. For proper unit operation, check refrigerant charge using charging information located on control box cover and/or in the Check Charge section of this instruction.

IMPORTANT: Maximum liquid-line size is 3/8-in. OD for all residential applications including long line applications.

IMPORTANT: Always install the factory-supplied liquid-line filter drier. Obtain replacement filter driers from your distributor or branch.

OUTDOOR WALL

INDOOR WALL

CAULK

LIQUID TUBE

 

INSULATION

SUCTION TUBE

 

THROUGH THE WALL

JOIST

HANGER STRAP

(AROUND SUCTION

TUBE ONLY) INSULATION

SUCTION TUBE

1” (25.4 mm)

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

MIN

 

 

 

 

 

 

 

LIQUID TUBE

 

 

 

 

 

 

 

 

SUSPENSION

A07588

Fig. 1 - Connecting Tubing Installation

Specifications for this unit in residential new construction market require the outdoor unit, indoor unit, refrigerant tubing sets, metering device, and filter drier listed in presale literature. There can be no deviation. Consult the Service Manual – Air Conditioners and Heat Pumps Using Puron® Refrigerant to obtain required unit changes for specific applications and for R-22 retrofit.

Check Equipment and Job Site

Unpack Unit

Move to final location. Remove carton taking care not to damage unit.

Inspect Equipment

File claim with shipping company prior to installation if shipment is damaged or incomplete. Locate unit rating plate on unit corner panel. It contains information needed to properly install unit. Check rating plate to be sure unit matches job specifications.

Install on a Solid, Level Mounting Pad

If conditions or local codes require the unit be attached to pad, tie down bolts should be used and fastened through knockouts provided in unit base pan. Refer to unit mounting pattern in Fig. 2 to determine base pan size and knockout hole location.

For hurricane tie downs, contact distributor for details and PE (Professional Engineer)Certification, if required.

On rooftop applications, mount on level platform or frame. Place unit above a load-bearing wall and isolate unit and tubing set from structure. Arrange supporting members to adequately support unit and minimize transmission of vibration to building. Consult local codes governing rooftop applications.

Roof mounted units exposed to winds above 5 mph may require wind baffles. Consult the Service Manual - Residential Split System Air Conditioners and Heat Pumps Using Puron® Refrigerant for wind baffle construction.

NOTE: Unit must be level to within ±2° (±3/8 in./ft,±9.5 mm/m.)per compressor manufacturer specifications.

Clearance Requirements

When installing, allow sufficient space for airflow clearance, wiring, refrigerant piping, and service. Allow 24 in. (609.6 mm) clearance to service end of unit and 48 in. (1219.2 mm) (above unit. For proper airflow, a 6-in. (152.4 mm) clearance on 1 side of unit and 12-in. (304.8 mm) on all remaining sides must be maintained. Maintain a distance of 24 in. (609.6 mm) between units. Position so water, snow, or ice from roof or eaves cannot fall directly on unit.

On rooftop applications, locate unit at least 6 in. (152.4 mm) above roof surface.

3/8---in. (9.53 mm) Dia. Tiedown Knockouts in Basepan(2) Places

View From Top

UNIT BASE PAN

TIEDOWN KNOCKOUT LOCATIONS in. (mm)

Dimension in. (mm)

A

B

C

35 X 35

9–1/8 (231.8)

6–9/16 (166.7)

28–7/16 (722.3)

(889 X 889)

 

 

 

 

 

 

A05177

Fig. 2 - Tiedown Knockout Locations

2

Image 2
Contents Indoor Thermostat Control Options Safety ConsiderationsUnit Operation and Safety Hazard Electrical Shock HazardClearance Requirements Install on a Solid, Level Mounting PadCheck Equipment and Job Site Unpack UnitMake Piping Connections Operating AmbientElevate Unit Outdoor Unit Connected to Factory-Approved IndoorAccessory Usage Liquid Rated Vapor Unit SizeMake Electrical Connections Compressor Crankcase Heater Airflow Selections ECM FurnacesSystem Functions And Sequence Of Operation Install AccessoriesStart-Up Time Delays Compressor OperationDefrost Liquid-Line Solenoid AccessoryInfinity Controlled low ambient cooling Defrost HoldCheck Charge 230V Line Power Disconnect Detection Pressure Switch ProtectionControl Fault Unloader Test ProcedureThermistor Sensor Comparison Temperature ThermistorsFailed Thermistor Default Operation Troubleshooting Status CodesEdge Thermidistat Models TP-PRH-01 or TP-NRH-01 Puronr R-410A Refrigerant Quick Reference Guide Care and MaintenanceFinal Checks Catalog No 25HPA6---1SI