Trucklift
3 Installation
3.1General Information
TRUCKLIFT is normally installed by the manufacturer's own trained technicians.
However, the lift can also be installed by the operator's own technical staff, provided that they are properly trained, with the necessary skills. It is important that they should have experience in the proper use of composite dowels and the proper installation of the electrical connections in accordance with the VDE regulations.
3.2Installation Location
The lift can be installed in any suitable location. The only restriction is that the standard version of the lift is not rated for use in rooms with explosive atmospheres
The installation location must be provided with the necessary power supply by the operator: 3~/N + PE 400/230 V, 50 Hz. The operator must also see to it that the power supply is protected with a T35A circuit breaker in accordance with the VDE 0100 regulation.
The standard point for the power supply cable inlet to the lift is at the top in the control column. However, the power supply cable can also be routed in through the hole provided in the baseplate. In both variants, the cable must be protected with a suitable cable support sleeve. The power supply cable must be connected to the terminals of the main switch in the control console on the control column.
Before installation, suitable foundations conforming to the specifications of the manufacturer MAHA must be provided. They must either be built specifically for installation of the unit, or the operator must provide evidence that they conform to the specifications. The installation location must be perfectly flat and level. If the foundations are installed in the open or in rooms where winter weather conditions or frost can be expected, the foundations must be sunk down to frost depth.
D1 | 7 |