3.0FREE CHLORINE SENSOR ASSEMBLY. The Free Chlorine Sensor is shipped with the membrane cap pre-installed and covered with a cap with water inside to keep the membrane wet. Make sure to keep sensor cap, anode and cathode inside the sensor body, away oily or greasy materials. Contact with oil or grease will result in inaccurate measurements.

NOTE: IF SENSOR WILL BE STORED DRY OUT OF FLOW

CELL, SHAKE BODY DOWNWARD INTO A SINK TO REMOVE THE FILL SOLUTION. TAKE THE MEMBRANE CAP AND IMMERSE IN A CUP OF TAP WATER UNTILL READY TO REUSE. SEE

SECTION 9. REPLACE CAP AND ELECTROLYTE BEFORE INSTALL- ING INTO FLOW CELL (see SECTION 10 for cap and electrolyte change. See SECTION 5 for sensor installation into flow cell).

SECTION 4.0

FLOW CELL INSTALLATION

4.0FLOW CELL.To obtain accurate Free Chlorine reading, the Sensor must be installed into the Flow Cell to prevent air bubbles formation on the membrane, proper spacing between the sensor and the installation wall, and laminar flow across the membrane.

4.1. Using two 1/4” NPT Tube fittings, connect the FC72 Flow

Cell into your system, noting the inlet (bottom) and outlet

(side) orientation. (see FIGURE 2)

4.2. Install clamp with rubber backing as shown in FIG. 2A.

4.3 Drill 3/8" diameter hole on the panel.

FC72 Flow cell

SENSOR

SNAP RING

GROOVE

THREADED FITTING

SNAP RING (INSTALLS INTO PROBE GROOVE)

O-RING

BARBED TUBE

FITTING

FLOW CELL

BARBED TUBE

FITTING

4.4

Insert bolt as shown in FIG 2A

4.5

On back of panel attach lock washer and nut to secure

 

clamp and flow cell to panel.

SECTION 5.0

SENSOR INSTALLATION

5.0SENSOR INSTALLATION INTO FLOW CELL.

a.First install threaded fitting onto sensor body (remove fitting if pre-installed in flow cell)

b.Install snap-ring into groove on sensor body

c.Next, slide o-ring onto body of sensor until it reaches bottom of threaded fitting.

d.Thread sensor assembly into top of flow cell as shown in FIGURE 2.

d. Turn on flow and verify the flow through the Flow Cell is at least 0.2gpm (45 liters/hour and no more than 0.6gpm (135 liters/hour).

FIG. 2A

M4679/0708 page 2 of 6

Parts covered by this product instruction sheet include: FCLTX-100 Series

Image 2
Contents Section Theory of Operation SectionSensor Installation Into Flow Cell Section Flow Cell InstallationSection Sensor Installation Section Sensor PreparationSection Electrical Installation Section Sensor ConditioningSection Calibration Section Sensor StorageSection Sensor Troubleshooting Troubleshooting ChartTechnical Specifications Section Sensor SpecificationFC72 Flow Cell Dimensions Operating Specifications