5.Attach the supporting legs to the housing bracket with 516"-18 x 12" flange bolts.

6.Position the base on top of the supporting legs (see Figure 8).

Flange Bolts

Figure 8. Base attached to supporting leg.

7.Fasten the supporting legs to the base with 516"-18 x 12" flange bolts.

8.With assistance, turn the entire assembly over so that the casters rest on the floor.

9.Position and hold the rubber gasket against the square opening in the main housing (see Figure 9).

Main Housing

Collector

Mounting Bolts

Rubber Gasket

Figure 9. Collector mounted to main housing.

10.With assistance, position and hold the collec- tor so the holes in the collector flange match with those of the rubber gasket and main housing.

11.Insert and hand tighten one 516"-18 x 1" flange bolt, two 516" flat washers, and one 516"- 18 hex nut in all eight holes.

12.Tighten the eight flange bolts and nuts in a alternating fashion so that the rubber gasket is evenly compressed without deformation.

13.Repeat Steps 10–13for the remaining col- lectors.

14.Place the inlet on the top center circular flange of the main housing (see Figure 10).

Screw

Figure 10. Inlet mounted on main housing.

15.Rotate the inlet so the hole in the inlet aligns with the hole in the housing flange.

16.Use the M6-1 x 10 Phillips head screw to fas- ten the inlet securely to the housing flange.

G0508 10 HP Industrial Dust Collector

-13-

Image 15
Contents Model G0508 HP Industrial Dust Collector Page Table of Contents Introduction ForewordContact Info Machine Data Sheet Impeller Information Identification G0508 10 HP Industrial Dust Collector Safety Instructions for Machinery Additional Safety for Dust Collectors 220/440V 3-Phase Grounding Rewiring toCircuit Requirements Unpacking SET UPSet Up Safety Items Needed for SetupInventory Contents Figure QtyFloor Load AssemblyPlacement Location Site ConsiderationsPage Page Lower collection bag secured to Collector To test run the dust collector Test RunMetal Duct Designing SystemGeneral Duct MaterialPlastic Duct Flexible DuctSketch a Basic Duct Layout System DesignDecide Who Will Design Sketch Your Shop LayoutDetermine Required CFM of Each Machine Machine ApproximateMachine Determining Main Line Duct Size Determining Branch Line Duct SizeTotal CFM Branch Line Size Calculating Duct Resistance System Grounding Blast Gate Metal Duct Starter Kit AccessoriesG6252-4 Floor Sweep G7341-5 Floor Sweep G7342-6 Floor Sweep Metal ElbowsMetal Branches Reducers & AdaptersH2443-Universal Adapter Dust collection pipe clampsOperations Daily Check MaintenanceLubrication Bag Cleaning ScheduleMotor & Machine Operation ServiceAbout Service TroubleshootingDesigning the System on Page 17 for more Dust Collection OperationElectrical Components G0508 220V switchWiring Diagram Parts Breakdown Description Parts ListLabel Placement Warranty and Returns Page Page Page