Kohler K-1840, 1071003-2-B manual Prepare the Site

Page 4

5-1/8"

(13 cm)

Wall

StudMaterial

Pocket

60"

Keyhole Saw

Levels

(152.4 cm)

Remove wall material.

2. Prepare the Site

IMPORTANT! Select wall material that is water resistant (such as cement board) and meets local building codes.

Install wall material to the entire shower area, including the stud pocket.

NOTE: Keep in mind the length of the column is 60″ (152.4 cm) when determining the desired height.

Determine the desired vertical position of the column at the stud pocket location, then draw a pencil mark at the base of the column.

From the marked point, draw a rectangle 60″ (152.4 cm) in height and 5-1/8″ (13 cm) in width.

Verify the drawn perimeter is plumb and level.

Using a keyhole saw, carefully cut along the marked perimeter lines to remove the wall material.

1071003-2-B

4

Kohler Co.

Image 4
Contents Installation Guide Tools and Materials Thank You For Choosing Kohler CompanyBefore You Begin Construct the Stud Framing Prepare the Site Install Shelves Assemble the UnitAssemble the Unit Install Top Cap Verify Fit Tile the Shower Area Complete the SiteVerify Fit Secure the Unit Merci d’avoir choisi la compagnie Kohler Outils et matérielsAvant de commencer Avant de commencer Construire le cadrage du montant Préparer le site Installer les étagères Installer le couvercle supérieurInstaller les tablettes Assembler l’unitéInstaller le couvercle supérieur Assembler l’unitéCompléter le site Vérifier lajustement Carreler lespace de doucheVérifier l’ajustement Carreler l’espace de doucheSécuriser l’unité Gracias por elegir los productos de Kohler Herramientas y materialesAntes de comenzar Antes de comenzar Construya la estructura de postes de madera Prepare el sitio Ensamble la unidad Instale los estantesEnsamble la unidad Instale la tapa superiorTermine el sitio Verifique que quede bienFije la unidad 1071003-2-B 1071003-2-B 1071003-2-B Kohler Co