LEAK TESTING

IMPORTANT:

VENTILATION

A minimum building ventilation rate of 4 CFM per 1,000 BTU’s of installed heater input must be provided. This rate of ventilation may be obtained through either gravity or mechanical ventilation of the building. In conjunction with building ventilation system, adequate fresh air into the building must be provided through fresh air inlets and/or building inlets. It is recommended local code be checked to assure the ventilation system and heat installation are in compliance with local and/or state codes.

When checking for gas leaks, do not use an open flame. Use a soap and water solution. Installation of 1/8”NPT plugged tapping, accessible for test gage connections, is required upstream of the gas supply connection to the heater.

NOTE: Gas connections on the heater are leak tested at the factory prior to shipment.

PRECAUTIONS:

Periodically check the whole gas system for leaks or immediately check if the smell of gas is detected. Extinguish all open flames.

Never leak test while smoking.

Do not use heater until all connections have been leak tested and do not leak.

When leak testing, refer to the connections diagrams.

Only those parts recommended by the manufacturer should be used.

Substitution can void warranty.

LEAK TEST:

Make a soap solution of one part liquid detergent, and one part water. The soap solution can be applied with a spray bottle, brush or rag, soap bubbles will appear where a leak is present.

Turn the gas supply “ON” check for leaks at leak points. If a leak is present, turn off supply, tighten any leaking fittings, turn gas on and recheck.

Note: There is a manual shut-off lever on the internal heater control valve/reg- ulator. This lever is shipped in the “ON” position (Default position).

"OFF"

"ON" POSITION

FACTORY DEFAULT

 

11

Image 12
Contents Professional DEL REY Heater Message to OUR Customers Please Retain this Manual for Future ReferenceTable of Contents Safety Practices and Precautions Insect WarningSafety Practices and Precautions CLEARANCES/INSTALLATION Specifications Installation Minimum Clearances to Combustible MaterialClearances Side ViewInstallation Minimum Clearances to NON-COMBUSTIBLE Material Side ViewPer bracket Installation InstallationGAS Inlet Pressure Mounting ElectricalGAS Piping Leak Testing PrecautionsVentilation Leak TestLIGHTING/OPERATION Instructions Lighting InstructionsTo Start Heater To Shut Down HeaterCare & Cleaning / Basic Troubleshooting Care and CleaningBefore Calling for Service Basic Troubleshooting Servicing Removal of BurnerGAS Valve Replacement GAS Valve Replacement Heater Parts List DescriptionWiring Diagram 120VAC 60 HzWiring Schematic Warranty Length of WarrantyDCS will Cover DCS will not CoverService HOW to Obtain ServiceBefore YOU Call for Service Page Page