Installation
1.Insert the unit downstream from an
Mount base on duct
using the enclosed mounting screws.
2. Insert lamp through hole. Place bracket over end of tube and tighten wing nut.
3. Replace cover on unit and tighten
side screw.
4.Plug into 120V outlet
& place rocker switch in “ON” position.
5.Switch will illuminate & blue glow can be seen through view port when unit is operating properly.
ALWAYS wear protective goggles to shield your eyes from UV damage when installing the
Installation Options
The
Good: Standard Installation
Better: Patented Angled Installation - Single Lamp
16"
Duct
Good
12"
Better
16"
Duct
18"
Best: Two Angled Lamps or Two Lamps Perpendicular
Note: When multiple lamps are used, spacing between lamps should be at least four inches. Angle option allows longer lamps to fit in smaller ducts.
16"
Duct
Best
18" |
18" |
18"
20"
Duct
18"
11