Trion 60 Outdoor Installations, Unpack and Inspect, Assemble Framework, Attach Adjoining Ductwork

Page 4

C.) The basin floor should be properly pitched and finished to prevent puddling.

D.) The cross members containing the anchoring studs to receive the air cleaner base frame must be even and level to provide a proper foundation for the metal framework base.

Where the installation site is not suitable for a poured concrete basin, rust resistant metal pans may be used. The metal should withstand the weight of service personnel in addition to the weight of the unit.

Each installation varies according to needs, but normally the controller is located near the air cleaner. Ideal mounting height is at eye level for ease in reading the instrumentation and to facilitate service.

For ease in maintenance and component removal, adequate space, 39” Minimum Required, must be provided in front of all access doors, motors, pump and accessory equipment.

3. Outdoor Installations

Requirements for outdoor protection vary in accordance to climate and equipment component arrangement for the particular job. The best approach, for equipment protection, is the construction of a heated shed or building over the installation. As an alternative, the installing contractor should treat the equipment as required to meet the specific needs.

Controller/PWM Power Supplies

As the controller/power supplies are designed for remote mounting, they can be, in many cases, located indoors and still be reasonably close to the main cabinet. If located outdoors with the cabinet, it must be weather protected.

Contact the local Trion Sales Office or the factory if questions arise, or any additional information is required.

SECTION II INSTALLATION

FOR THE INSTALLING CONTRACTOR

1. Unpack and Inspect

At the time the unit is received, all shipping containers and their contents should be examined for damage. Any damage occurring in shipment must be immediately reported to the carrier, an inspection report completed and a claim filed at the receiving point.

The number of shipping containers included in the shipment is dependent upon the unit size and type. When packaging the material for shipment, consideration is given to grouping the components into the installation categories in which they will be used. The packing list included with shipment identifies the various items to a specific box number. In general, the grouping is as follows:

(A)Framework

(B)Ionizing-Collecting Cells

(C)Controller with Power Supplies

(D)Accessories

For the protection of the components, it is recommended that those materials not immediately needed for installation be stored in the container in which they are received in a safe, dry and clean location. This is particularly true with the ionizing- collecting cells, which may be damaged when not properly handled.

2. Assemble Framework

The base frame, two sides and top are match marked on the air entering side of the air cleaner at the factory prior to shipment. See Figure 5.

(A)Position the base frame on the drain basin. Make sure it is located with the marking “BOTTOM FRONT” on the air entering side. The anchoring studs in the drain basin should be located on the inside of the frame channels and the entire frame should be level. Shim as necessary.

(B)Secure the base as illustrated. It is important that the studs do not protrude above the base frame channel. Cut top of studs, if necessary. Each anchor should be treated to prevent rust.

(C)Attach the side and top panels, match marking where the pieces join on the air entering side; A to A, B to B, etc. The required fasteners are packaged and marked for the framework.

(D)After the outside frame structure is complete, position and secure the intermediate cell supports. The side to receive the air bypass strips marked “FRONT” should be positioned toward the air entering side.

3. Attach Adjoining Ductwork

Depending on the application, the installation plan may or may not call for adjoining ductwork on the air entering and/or air leaving sides of the cabinet.

When adjoining ducting is to be installed, attach to the flanges on the air entering and air leaving sides of the unit. Maintain structural squareness during attachment.

The seam should be made air and watertight by caulking or gasketing.

The seam between the concrete drain basin and the metal work must be caulked or grouted to form a good watertight seal.

When a blower is installed downstream from the Trion cabinet, the ducting between the cabinet and the blower

4

Image 4
Contents AIR Boss Model 60 Series Not Used General Description System Design and Floor LayoutOutdoor Installations Unpack and InspectAssemble Framework Attach Adjoining DuctworkInstall Ionizing-Collecting Cells Install Air By-Pass BafflesComplete Wiring A. High Voltage Wiring Disconnect Switch and Pilot LightsIntroduction and Principle of Operation Initial Start-upRoutine Maintenance Washing FrequencyTroubleshooting Spare Parts LEDTroubleshooting Reference Chart Problem Probable Location Reason Correction Symptom CausePage Page Page Page Page Page Page Page Page Page Page Page Page Page Model 60 Control Schematic Model 60 Field Wiring Page

60 specifications

The Trion 60 is a cutting-edge device designed for advanced computing needs, featuring a blend of robust architecture and innovative technologies. This powerful system is ideal for both professional and personal users seeking top-tier performance.

One of the standout features of the Trion 60 is its processing power. It is equipped with a state-of-the-art multi-core processor that enables seamless multitasking and exceptional speed across various applications. Whether handling complex data analysis, rendering graphics, or managing multiple open applications, the Trion 60 delivers outstanding efficiency and reduces latency, making it a reliable choice for demanding tasks.

In addition to its powerful processor, the Trion 60 incorporates high-speed RAM that significantly enhances overall performance. With expandable memory options, users can tailor the system to their specific requirements, ensuring that it can handle increasing workloads without compromising speed or performance.

Graphics performance is another critical aspect of the Trion 60. Featuring a dedicated graphics card, this device supports high-fidelity visuals and smooth rendering, making it suitable for creative professionals, gamers, and anyone who requires exceptional graphic capabilities. The advanced graphics technology enables immersive experiences in both gaming and media consumption.

Connectivity is a strong suit of the Trion 60, which comes equipped with multiple ports and options for both wired and wireless connections. This includes USB 3.0 and 3.1 ports for rapid data transfer, HDMI and DisplayPort for multi-monitor setups, and Wi-Fi 6 capabilities, ensuring fast internet access and stable connections.

Security features are intelligently integrated into the Trion 60, with options for biometric authentication and advanced encryption to protect sensitive data. This focus on security makes it an excellent choice for business environments where data integrity is paramount.

The Trion 60 is built with a sleek and modern design, offering not just functionality but also aesthetic appeal. Its compact form factor makes it easy to integrate into various workspaces, while optimized cooling systems ensure silent operation even under heavy loads.

Overall, the Trion 60 combines power, versatility, and security, making it an ideal solution for anyone looking to elevate their computing experience. With its range of features and technologies, it stands out as a leading choice in its category, poised to meet the demands of today’s users.