User’s Information Manual

2 Maintenance schedule (continued)

4.Fill with fresh water until the water begins to pour out of the drain.

5.Replace the cap. Press the cap onto the trap until the cap makes contact with the drain.

6.Replace the retaining screw.

The condensate trap (FIG. 2-1) must be ￿ WARNING filled with water during all times of boiler

operation to avoid flue gas emission from the condensate drain line. Failure to fill the trap could result in severe personal injury or death.

Figure 2-1Condensate Trap

NOTICE

Use materials approved by the authority

having jurisdiction. In the absence of

 

 

other authority, PVC and CPVC pipe

 

must comply with ASTM D1785 or D2845.

 

Cement and primer must comply with

 

ASME D2564 or F493. For Canada use

 

CSA or ULC certified PVC or CPVC pipe,

 

fittings, and cement.

 

To allow for proper drainage on large

NOTICE

horizontal runs, a second line vent may

 

be required and tubing size may need to

 

increase to 1 inch.

The condensate line must remain unobstructed, allowing free flow of condensate. If condensate is allowed to freeze in the line or if the line is obstructed in any other manner, condensate can exit from the boiler tee, resulting in potential water damage to property. Call your qualified service technician to inspect the boiler and system.

7.A condensate removal pump is required if the boiler is below the drain. When installing a condensate pump, select one approved for use with condensing boilers and furnaces. The pump should have an overflow switch to prevent property damage from condensate spillage. Call your qualified service technician to inspect the boiler and system.

Condensate disposal

1.This boiler is a high efficiency appliance that produces condensate.

2.The bottom of the boiler has a 1/2 inch pipe for connection of a 1/2 inch PVC pipe (FIG. 2-2).

3.Slope condensate tubing down and away from the boiler into a drain or condensate neutralizing filter. Condensate from the Knight wall mount boiler will be slightly acidic (typically with a pH from 3 to 5). Install a neutralizing filter if required by local codes. Call your qualified service technician to inspect the boiler and system.

A Neutralizer Kit is available from the factory (Kit #3087). Call your qualified service technician to install.

4.Do not expose condensate line to freezing temperatures.

5.Use only plastic tubing or piping as a condensate drain line (FIG. 2-2).

6.Leave the top of the tee assembly installed in the unit open, this is needed as a vacuum break. The blocked drain switch will shut the boiler down before any condensate can flow out of the tee.

Figure 2-2Condensate Disposal

CONDENSATE TRAP

REMOVABLE CAP

FOR CLEANING TRAP

CONDENSATE DRAIN CONNECTION - ROUTE TO FLOOR DRAIN OR NEUTRALIZING FILTER USING:

1/2" PVC PIPE & FITTINGS or 1/2" CPVC PIPE & FITTINGS or 5/8" I.D. PLASTIC TUBING (FIELD SUPPLIED)

7

Image 7
Contents User’s Information Manual Models 51 Contents Please read before proceeding Boiler service and maintenanceProducts to avoid Prevent combustion air contaminationAreas likely to have contaminants Owner maintenance Maintenance schedule Service technicianSee pages 6 8 for detailed instructions Fill condensate trap with water Maintenance scheduleCondensate disposal 1Condensate TrapCheck air vents Operating instructions Smart System control module InstallerUser Night Setback Override Temperature UnitsSpace heating SH1, SH2, SH3 and tank set points Call for Heat Information Dial Function User’s Information Manual
Related manuals
Manual 80 pages 15.82 Kb