Middleby Marshall PS520 Conveyor Reassembly Into Oven, Checking Conveyor Belt Tension

Page 36

SECTION 4

MAINTENANCE

E. Conveyor Reassembly Into Oven

1. Lift conveyor and position it in oven as shown.

NOTE: Conveyor may be inserted into either end of oven. If it is to be installed from the non-drive end of the oven the drive sprocket assembly must be removed as shown in conveyor disassembly section.

F. Checking Conveyor Belt Tension

WARNING

Oven conveyor belt must be cool when adjusting belt. Do not adjust belt if HOT.

1.With the conveyor assembly in the oven, stand at one end of conveyor and check tension by lifting the conveyor

belt at the center of the oven chamber opening. The belt should not lift higher that 1to 2(75mm to 102mm).

2.If conveyor belt is still not under proper tension, an entire link must be removed. Use the following procedure “H. Conveyor Belt Link Removal” to remove a link. If conveyor belt is under proper tension proceed directly to “J. Attaching Drive Chain”.

Figure 4-21.

2. Reinstall the conveyor extension.

Conveyor Extension

Figure 4-23.

Figure 4-22.

32

Image 36
Contents Owners operating Page Middleby Marshall Table of Contents Section Description Model IdentificationPS520 Series Oven Specifications Series PS520 Electrical SpecificationsThis Manual Must Be Kept For Future Reference PS520-Series Oven Components Locations II. Component Function Cooling Fan Blank Plates two sizes and an Air Finger F2. Blank PlatesSection Installation UnloadingParts List for Series PS520 Electric Oven Installation KIT Single and Double Stack OvensModel PS520 Single Oven Dimensions Model PS520 Double Oven Dimensions Model 520 Triple Oven Dimensions II. Ventilation Guidelines Electric Supply to be Provided by Customer CircuitbreakerIV. Electric Supply for Electrically Heated Ovens 10. Typical Electric Oven Data PlateSection Installation Section Operation Control FunctionsII. Component Information and Location Figures 3-1 Measuring Conveyor Speed ConveyorStartup Procedures Daily Startup III. STEP-BY-STEP OperationControl Panel Daily Startup Procedure IV. Normal Operation STEP-BY-STEPSP Lock Quick Reference Troubleshooting SymptomSection Maintenance Maintenance Daily ExteriorCooling Fan Conveyor Belt FigureII. Maintenance Monthly Removing Conveyor From Oven For CleaningAir Fingers Disassembly For Cleaning T1 T2 T3 B1 B2 B3 Reassembly of Air Fingers 12. Standard Lower FingerExtended Lip Tab on Outer Plate Flange Finger Manifold Section Maintenance Reinstall End Plugs Conveyor Reassembly Into Oven Checking Conveyor Belt TensionConveyor Belt Link Removal Attaching Drive Chain III. Maintenance Every 3 Months IV. Maintenance Every 6 MonthsImportant Notices Electrical TerminalsKEY Spare Parts KIT PS520-SERIES Electric Oven KEY Spare Parts KIT FigureSection Troubleshooting Section Troubleshooting Parts List English Single Oven Exploded View English Relay Panel English Blower Assembly English Control Panel English Single Conveyor Section Parts List Section Electrical Schematics Wiring Diagram, E380-480V 50/60/1, PS520 Wiring Diagram, E230-240V CE PS520/1820S Wiring Diagram, E380-400V CE PS520/1820S Section Electrical Schematics