Generac Power Systems 005262-0 owner manual Service Schedule

Page 20

Standby Generator Sets

Service Schedule

SERVICE SCHEDULE

30 KW - 150 KW STANDBY GAS ENGINE DRIVEN GENERATOR SETS

The following is a recommended maintenance schedule for standby gas engine driven generator sets from 30kW to 150 kW in size. The established intervals in the schedule are the maximum recommended when the unit is used in an average service application. They will need to be decreased (performed more frequently) if the unit is used in a severe application. Use calendar time, from the previous maintenance interval to determine the next required maintenance interval.

Service Maintenance Interval Information:

The various service maintenance intervals are designated by interval numbers as follows:

1An early inspection of the generator set to insure it is ready to operate when required and to identify any poten- tial problem areas.

This inspection may be performed by the end user providing the following safety steps are taken to prevent the engine from starting automatically without warning:

To prevent injury, perform the following steps in the order indicated before starting any maintenance:

Disable the generator set from starting and/or connecting to the load by setting the control panel Auto/Off/ Manual switch to the “OFF” position.

Remove the 15 amp control panel fuse.

Turn off the battery charger.

Remove the negative battery cable.

The battery charger must be turned off BEFORE removing the battery cable to prevent an over current condition

from burning out sensitive control panel components and circuits.

Following all maintenance, reverse these steps to insure the unit is returned to standby setup for normal operation when required.

2A wear-in service inspection of the generator set to insure it is ready to operate and carry the load when required, and to identify any potential problem areas.

Performed ONLY ONCE following the first three months or the first 30 hours of operation after purchase of the unit.

This inspection contains some maintenance tasks which require special tools, equipment, and/or knowledge to accomplish and should be performed only by an Authorized Service Dealer.

3An operational inspection of the generator set to insure it is ready to operate and carry the load when required, and to identify any potential problem areas.

Performed semi-annually or following each 50 hours of operation of the unit.

This inspection contains some maintenance tasks which require special tools, equipment, and/or knowledge to accomplish and should be performed only by an Authorized Service Dealer.

4A mid-level inspection of the generator set to insure it is ready to operate and carry the load when required, and to identify any potential problem areas.

Performed annually or following each 100 hours of operation of the unit.

This inspection contains some maintenance tasks which require special tools, equipment, and/or knowledge to accomplish and should be performed only by an Authorized Service Dealer.

5A comprehensive inspection of the generator set to insure it is properly serviced and ready to operate and carry the load when required, and to identify any potential problem areas.

Performed annually or following each 250 hours of operation of the unit.

This inspection contains some maintenance tasks which require special tools, equipment, and/or knowledge to accomplish and should be performed only by an Authorized Service Dealer.

11-1

09/05 A .Rev SrvSchd001

Image 20
Contents Model Standby Generator Sets Table of Contents  Warning   Electrical Hazards  ‹ Operation and Maintenance ‹ HOW to Obtain ServiceAuthorized Service Dealer Location IntroductionIdentification Record ‹ Data LabelCoolant Recommendations Equipment DescriptionEngine OIL Recommendations Engine Protective Devices Fuel System ‹ Fuel Requirements‹ Natural GAS Fuel System ‹ LP Fuel SystemSpecifications ‹ Reconfiguring the Fuel System ‹ Cold Weather KITAlternator Power Winding Connections ‹ FOUR-LEAD, SINGLE-PHASE Stator‹ 3-PHASE Alternators Generator AC Lead ConnectionsInitial Inspection for QT Genset Startup InstallationPreparation Before START-UP ‹ START-UP Inspection START-UP Checklist‹ Preparation for START-UP Operating Unit with Manual Transfer Switch Generator Control Operation‹ Engine START-UP and Transfer ‹ Retransfer and ShutdownCooling System Checking Fluid LevelsMaintenance Owner Operator can Perform ‹ Spark Plugs ‹ Changing the Engine AIR Cleaner ‹ Coolant Change‹ Changing Engine OIL Miscellaneous Maintenance ‹ Cleaning the Generator‹ Battery ‹ Battery MaintenanceService Schedule KW 150 KW Standby GAS Engine Driven Generator SetsMaintenance Level 11-3 11-4 Troubleshooting Guide Problem Cause CorrectionStandby Generator Sets Standby Generator Sets Standby Generator Sets Page PAN CB Conn BOX Page UL Circuit Breaker QJ-2P Page Instr Hypot Test not Shown Page Components Included in 0F9696E Page Weldment Frame 2.4L C2 Page Battery Tray C1 CPL Page Engine 2.4L G1 Page Weldment Radiator Support 2.4L Page Gasket Bosch 32 Page Flange Fuel Inlet Page Rear Wrap C2 CPL Page Bracket Muffler Page Page Page Page Page Page Page Page Page Page Page C2 Units Standby Generator Sets Warranty