4.4 Installing a Proven Draft Switch

A safety system must be interlocked with the appliance. The safety system could utilize a Proven Draft Switch (PDS-1), a thermal switch, a flow switch or a sail switch. The device must be interlocked with the heating appliance(s) so it shuts down in case of insufficient draft, fan failure or power failure. Please refer to

the PDS Installation Manual for wiring instructions.

If the installation includes an EBC12 or EBC 30 Fan Control, a PDS-1 is not required as the function is integrated in the control.

For more information about alternative safety system, please consult EXHAUSTO.

4.5 Installation of Stack Probe for PDS Function

Install the probe for the Proven Draft Switch (PDS-1) in the vent connector. The probe must be located between the appliance and the power venter. The probe must be located at least 3 vent diameters downstream of the draft hood, draft diverter, or barometric damper. The probe placement should also observe distances from elbows and Tees as shown in figure below. The tip of the probe MUST be flush with the inner chimney wall to

get a proper pressure reading.

Fig. 12

11

Image 11
Contents Rsib 300-500 Power Venter Symbol Legend Components FunctionShipping WarrantyCapacity SpecificationsDimensions & Capacities Positioning Mechanical InstallationGeneral Figure below shows typical installation arrangements Mounting of Power VenterConnection to Flexible Duct Connection to Chimney or VentWiring Diagram Rsib Electrical InstallationProven Draft Switch Installation of Stack Probe for PDS Function Installing a Proven Draft SwitchChecking and Changing Rotation of Rsib 350, 400, Testing Safety System Startup and ConfigurationSystem Testing Adjusting Fan SpeedPreparing the Power Venter for Cleaning Maintenance and TroubleshootingFan is not running TroubleshootingRsib 300, 350, 400