Post-installation Checklist 27
Follow the parameters defined in Tab le 30 for binding cables with ties.
Post-installation Checklist
After you install your Switch 8800, use the checklist in Tab le 31 to verify that your
switch operates correctly.
WARNING: Confirm that you have turned off the power before checking your
installation. Improper connections can injure people or damage components of
the switch.
Tabl e 30 Cable Binding Parameters
Cable Bundle Diameter Space Between Bundles
10 mm (0.5in) 80 – 150 mm (3.5 – 6 in)
10 – 30 mm (.5 – 1.2 in) 150 – 200 mm (6 – 8 in)
30 mm (1.2 in) 200 – 300 mm (8 – 12 in)
Tabl e 31 Installation Checklist
Item Normal Abnormal (Remarks)
Antistatic wrist strap
Console cable
Ground wire
Power cord
Fabric
I/O module
Fan frame
Power supply