A template is provided with the cabinet isolation gasket. The template may be used to determine the cable conduit locations. Place the template over the top of the PMF and align the top right corner of the template with the top right corner of the PMF as shown in Figure 3. The holes punched in the template show the locations for the conduit within the PMF.

 

CUT-OUT INDICATES

 

CUT-OUT INDICATES

LOCATION OF

 

LOCATION OF FEEDER

DISTRIBUTION

 

CABLE CONDUIT

CABLE CONDUIT

ALIGN EDGES OF

 

 

 

 

TEMPLATE WITH

 

 

EDGES OF PMF

21937-A

FRONT OF

PLACE CARDBOARD

TEMPLATE OVER

TOP OF PMF

CABINET

Figure 3. Using the Template To Determine Duct Location Within the PMF

4 CONCRETE PAD CONSTRUCTION

Use the following procedure to construct the concrete pad:

1.Build a wood form for the concrete pad using 2 x 6 framing lumber as shown in Figure 4.

2.Locate the PMF using the dimensions provided in the construction diagram (see Figure 2). When installed, the top surface of the PMF must be flush and level with the top of the concrete pad.

Note: Use temporary top framing to keep the top surface of the PMF flush and level with the top of the concrete pad (see Figure 4) while the concrete is poured.

3. Place reinforcing material inside the form but outside of the PMF.