Installation

Mechanical Installation (Continued)

Base Frame

Locknut

2"

 

3 1/2 x 2 Inch

(51 mm)

 

Dia. Bolt

 

 

 

 

Grout

6"

MIN

 

(152 mm)

Anchor

 

 

 

 

Bolt

U095IEP

Figure 8

After the anchor bolts are installed and the concrete has cured, proceed as follows:

1.Place the washer-extractor adjacent to the foundation. Do not attempt to move it by pushing on the sides. Always insert a pry bar or other device under the bottom of the frame of the washer-extractor to move it.

2.Remove the wood skid by unscrewing the carriage bolts holding it to the bottom frame of the washer-extractor.

3.Place the washer-extractor carefully over the anchor bolts. Never attempt to lift the machine by the door handle or by pushing on the cover panels.

4.Raise and level the washer-extractor 1/2 inch off the floor on three points, using spacers such as nut fasteners.

20

5.Fill the spaces between the washer- extractor base and floor with a good quality non-shrinking machinery grout to ensure a stable installation. See Figure 9 for grouting the 35-pound capacity model. See Figure 10 for grouting the 50-pound capacity model. See Figure 11 for grouting the 85-pound capacity model.

U096I

Figure 9

U097I

Figure 10

F232058