AIS® 3000 10-40kVA, 400V, Site Preparation and Installation Manual – 990-2258 43
Leveling Feet
Setting the leveling feet
Set the leveling feet to ensure the UPS is horizontal when it is in its final operating position. Use a 13/
14-mm wrench (shipped with UPS) to adjust all 4 leveling feet from front to back, and left to right,
until the pads make solid contact with the floor. Use a level tube to check the Enclosure is horizontal.
Verify that the installation has been electrically wired before setting the leveling feet.
CAUTION!
To avoid equipment damage, do not push or pull the UPS after the leveling feet have
been lowered.
Remember to install the Front Panel. See Front Panel section for details.
If Battery Securing is required, carry out this procedure prior to installing the Front Panel.
13/14-mm wrench